REPORT #7427
BY: FINANCE COMMITTEE, Lawrence R. Pei-nick, Chairman
IN RE: PRE-APPLICATION GRANT FOR SOLID .WASTE RESOURCE RECOVERY IMPLEMENTATION
C. PROGRAM
TO: THE OAKLAND COUNTY BOARD OF COMMISSIONERS
Mr. Chairman, Ladies and Gentlemen:
The Finance Committee has reviewed the Pre-application for Municiple Solid
Waste Resource Recovery Implementation Grant Program and the financial implica-
tions of the Grant to Oakland County.
It has been estimated $165,600 for solid waste implementation studies as
detailed in the schedule below:
February 5, 1976
12 months, total
3 months
3 months
1 month
2 months
3 months
2 months
Technology Assessment
Preliminary Cost and Economic Analysis
Recovery System and Site Selection
Transportation, Cost Refinement and
Preliminary System Planning
Conceptual System Design
Financing, Implementation Planning, Preparation
and Analysis of Responses to a Request for
Proposals
(due to interrelating and overlapping tasks
where possible)
Oakland County would be expected to provide 25% or $41,400 of the $165,600.
The remaining 75% or $124,200 would consist of Federal grant funds.
Pursuant to Miscellaneous Resolution 7059 of 4-17-75 the County of Oakland
has committed itself to pursue the construction of a Solid Waste Resource Energy
Conversion Facility. To this end, the Oakland County Board of Commissioners appropriated
$250,400 in the 1976 Public Works Budget. Thus acceptance of this grant would reduce
the County's financial commitment by the amount of Federal Funds received.
FINANCE COMMITTEE
-1.
February 5, 1976
Moved by Pernick supported by Moffitt the report be accepted.
A sufficient majority having voted therefor, the motion carried.
The chairman referred the report to the Planning and Building committee.
There were no objections.