HomeMy WebLinkAboutResolutions - 2014.04.30 - 21316MISCELLANEOUS RESOLUTION #14099 April 30, 2014
BY: PLANNING & BUILDING COMMITTEE, JIM RUNESTAD, CHAIRPERSON
IN RE: WATER RESOURCES COMMISSIONER - OAKLAND COUNTY BUILDING
RENOVATIONS AT 2636 DIXIE HWY., WATERFORD TOWNSHIP, MI
To The Oakland County Board of Commissioners
Chairperson, Ladies and Gentlemen:
WHEREAS the Water Resources Commissioner (WRC) has determined that
consolidating its billing and payment offices into one location will improve operational efficiencies;
and
WHEREAS pursuant to authorization by way of MR #13311, a building was purchased at
2636 Dixie Highway, Waterford Township, MI with renovation costs estimated at $254,000; and
WHEREAS closing for the building was completed on February 4, 2014; and
WHEREAS the building is larger than needed for billing services and at the time of the
initial purchase WRC had not determined how the additional space would be used; and
WHEREAS WRC has decided that a portion of the Water Maintenance department will
move to this new location; and
WHEREAS WRC has requested assistance from Facilities Management to manage
renovations at the 2636 Dixie Highway, Waterford Township, MI, location; and
WHEREAS architectural and electrical drawings were completed and bid documents
were released on March 12, 2014; and
WHEREAS Facilities Managements annual (competitively bid) construction manager,
George W. Auch Company, was selected to manage the project and sub-contract all
trades; and,
WHEREAS bids were opened on March 26, 2014 and low bids were tabulated.
WHEREAS additional monies are needed in the amount of $231,942 and includes $5,436
in closing cost and prorated taxes, $111,415 for construction renovation, $8,408 network
adjustment to fiber, $41,945 in network cabling and phone system equipment, $7,000 for property
sign, $3,000 for parking lot adjustments, $8,000 for roof leak, $30,238 for project contingency to
cover unknown variables and $16,500 for Water Maintenance staff furniture and
WHEREAS funding is available from the water and sewer trust funds in the amount of
$115,971 and the Pontiac water and sewer funds in the amount of $115,971,
NOW THEREFORE BE IT RESOLVED that the Oakland County Board of Commissioners
authorizes additional project costs in the amount of $231,942 associated with the cost of
renovations of the building at 2636 Dixie Highway, Waterford, MI.
Chairperson, on behalf of the Planning & Building Committee, I move the adoption of the
foregoing resolution.
PLANNING & BUILDING COMMITTEE
,.-79;er>
PLANNING & BUILDING COMMITTEE VOTE:
Motion carried unanimously on a roll call vote.
Motion for Rule IX.E. Direct Referral to Finance carried on a voice vote.
Form DC-001
OAKLAND COUNTY
WATER RESOURCES COMMISSIONER MEMORANDUM
TO: Commissioner Runestad
FROM: Phil Sanzica and Sherri Gee
SUBJECT: WRC Billing Center Building
DATE: April 15, 2014
Summary: The purpose of this memorandum is to update the Budget Task Force regarding the
acquisition and renovation of the new Billing Center building for WRC authorized per MR#13311 that
was adopted December 12, 2013. As the project has moved forward and bids have been received for
the renovation WRC finds it will need to transfer an additional $231,942 from the water and sewer
reserves, as well as the Pontiac water and sewer funds.
History: In December 2013, WRC brought to the Budget Task Force and the Board of
Commissioners a resolution to purchase a building located at 2636 Dixie Highway in Waterford. The
purchase agreement was signed by the Board of Commissioners and the closing was completed on
February 4, 2014.
The intended purpose of the building is to consolidate billing services operations for all WRC
customers, including Pontiac. The building is larger than is needed for billing services alone. WRC
had not finalized plans on how it might utilize the remainder of the building when the request to
purchase was brought to the Board of Commissioners.
The original Fiscal Note for MR#13311 totaled $569,475, which included the purchase price of the
building, at $315,000 and estimated one-time renovation and moving costs at $254,475.
At the time the Fiscal Note was drawn up, architectural plans had not been developed for the building
and the project had not been fully scoped out. The project budget was developed utilizing estimates
provided in part by the Auch Company, an FM&O contracted construction manager, OCIT, and
Facilities Management. WRC was working under time constraints imposed by the purchase
agreement and sought to provide as complete and accurate project estimate as possible.
Developments: After securing approval for the purchase of the building and the one-time project
costs as estimated, WRC determined it would be appropriate to also move the portion of the Water
Maintenance department that works closely with the Billing department to the new building.
After WRC took occupancy on February 4, 2014, architectural drawings were developed and the
project was further defined with IT and Facilities Management. Bid documents were released on
March 12, 2014 and opened on March 26, 2014. Clarifications were completed the week of March 31,
2014, and final costs were reviewed on April 7, 2014. Facilities Management's annual (competitively
bid) construction manager, George W. Auch Company, was selected to manage the project and
contract all trades.
OAKLAND COUNTY WATER RESOURCES COMMISSIONER
Page 1 of 1
Rev.: 11/05/08
Form DC-001
The issues impacting project costs are summarized below:
1) Closing costs and prorated taxes associated with the purchase were not included in the project
estimate. Cost impact: $6,436
2) Building code, life safety, and security issues were identified during development of the
renovation plan that have increased the cost of construction. Examples include provision for
emergency lighting throughout the building, replacement of doors separating public and staff
for security, and associated wall patching and painting. Cost impact: $44,000
3) The electrical capacity for the building needs to be increased to accommodate the loads
created by computers for both Billing and Water Maintenance. While this was anticipated in the
initial construction estimates, higher than anticipated contractor and DTE costs have been
realized as a result of bidding and DTE service requirements. Cost impact: $12,000
estimated. This amount may increase based on DTE actual work.
4) OCIT initially quoted network services for the building at $5,600 for the connection and $650
per month recurring cost. OCIT later determined it is able to move a fiber connection from the
old "Anderson Engineering" building east of the Billing Center and eliminate the recurring
monthly fee. However, the one-time cost for relocation is higher, at an estimated $14,008.
Long term the ability to eliminate the recurring charge makes the ROI roughly 15 months.
Cost impact: $8,408
5) The quote for network services did not include network cabling costs within the building. In
addition, it was not realized that the phone system in use at 95 Public Works could not be used
at the new location, resulting in an unanticipated cost for new phone equipment. Cost impact:
$41,945
6) The addition of Water Maintenance staff to the building required the acquisition of additional
furniture and millwork for counters. In addition, although originally excluded from the project, it
is now necessary to build a ramp to the back door to bring meters into the building on a cart.
The quoted ramp is wood with concrete supports. We may need to upgrade to a concrete
ramp. Cost impact: $44,500 ($16,500 furniture + $20,000 ramp + $8,000 millwork and
blocking)
7) An issue with property limits and easements place the existing building sign on the adjacent
property. VVRC was not able to resolve this issue with the property owners prior to closing the
sale. While we continue to attempt an equitable solution for both parties, we will need to go
before Waterford Township's Zoning Board to gain a variance for installation of new signage or
incorporation of the existing sign through agreement with the adjacent property owners. Cost
impact: $7,000
8) Site improvements were not included in the project. With the inclusion of Water Maintenance
staff to the building it is necessary to reconfigure the lot to provide several additional parking
spaces. Removal of a planting bed, subsequent asphalt patching and restriping of the lot are
necessary. Cost impact: $3,000
OAKLAND COUNTY WATER RESOURCES COMMISSIONER
Page 2 of 2 Rev.: 11/05/08
Form DC-001
9) Over the course of the winter the roof membrane was damaged and the roof leaked. Facilities
Maintenance had the roof repaired using an annual contractor. Evaluation of the roof indicates
several improvements can be executed to improve water management at the parapet. Cost
impact: $8,000
10)With increased costs, the contingency for construction costs needs to increase as well. Cost
impact $8,400 (10% of items 2, 3, and 6 (less furniture)
11)Construction Management costs/fees and related costs are based on actual renovation costs
as bid. The scope of work has been expanded due to the inclusion of Water Maintenance as
well as other factors mentioned above; therefore, Auch's fees have increased. Cost impact:
$19,000
Conclusion: The items above total $201,689. The items that are estimated and may increase once
work begins include electrical costs from DIE, patching and painting, ramp at back entrance, property
sign and potential easement, and estimated roof repairs. Because there are still many variables to
consider before the project is completed, we are requesting a 15% contingency of $30,253.
We are proposing to transfer 50% of the total from the Water & Sewer Trust Fund, for a total of
$115,971. Previously, we transferred $113,756 from this fund. The water reserve has a current fund
balance of 2.1 million and the sewer reserve has a current fund balance of 2.3 million.
We are proposing to transfer 50% of the total from the City of Pontiac Water and Sewer funds into the
Drain Equipment Fund, for a total of $115,971. Previously, we transferred $55,990 from these funds.
The City of Pontiac did not previously pay into the Water & Sewer Trust Fund.
OAKLAND COUNTY WATER RESOURCES COMMISSIONER
Page 3 of 3
Rev.:11/05/08
Form DC-001
Summary:
Item Estimate Actual Difference Comments
Building Purchase $315,000 $320,436 ($5,436) Includes pro-rated property taxes and title fee
Construction $118,875 $230,290 ($111,415)
Safety & Security $0
Electrical Capacity $0
Water Maintenance $0
Cameras $30,000 $30,000 $0 Still an estimate until work completed.
Network $5,600 $14,008 ($8,408) Fiber instead of AT&T connection
Network Cabling & Phone System $0 $41,945 ($41,945) Not included in original network quote
Property Sign $0 $7,000 ($7,000) Still an estimate until work completed.
Parking Lot $0 $3,000 ($3,000) Not needed prior to Water Maintenance unit occupying building
Roof $0 $8,000 ($8,000) Roof leak
Furniture $100,000 $116,500 ($16,500) Water maintenance furniture
SUB-TOTAL: $569,475 $771,179 ($201,704)
Project Contingency (15%) 0
.._,
$30,238 ($30,238)
TOTAL: $669,475 $801,417 ($231,942)
OAKLAND COUNTY WATER RESOURCES COMMISSIONER
Page 4 of 4 Rev.: 11/05/08
FISCAL NOTE (MISC. #14099) April 30, 2014
BY: FINANCE COMMITTEE, TOM MIDDLETON, CHAIRPERSON
IN RE: WATER RESOURCES COMMISSIONER — OAKLAND COUNTY BUILDING RENOVATIONS AT
2636 DIXIE HWY., WATERFORD TOWNSHIP, MI
TO THE OAKLAND COUNTY BOARD OF COMMISSIONERS
Chairperson, Ladies and Gentlemen:
Pursuant to Rule XII-C of this Board, the Finance Committee has reviewed the above referenced
resolution and finds:
1. The Resolution authorizes an additional $231,942 in acquisition and renovation cost
needed to complete the Water Resources Commissioner's (WRC) new office building at
2636 Dixie Highway in Waterford Township.
2. The new building for WRC was authorized per MR#13311 to allow billing personnel to be
located in one location for enhanced operational efficiencies and improved customer
service. A portion of the Water Maintenance department that works closely with the
Billing department will also move to the new building.
3. Facilities Management construction manager George W. Auch Company was selected to
manage the project and sub-contract all trades.
4. The additional cost includes $5,436 in closing cost and prorated taxes, $111,415 for
construction renovation, $8,408 network adjustment to fiber, $41,945 in network cabling
and phone system equipment, $7,000 for property sign, $3,000 for parking lot
adjustments, $8,000 for roof leak, $30,238 for project contingency and $16,500 for Water
Maintenance staff furniture.
5. The following budget amendment is recommended for Fiscal Year 2014:
Drain Equipment Fund (63900)
Revenue
6010101-149750-695500-57010-26486 Transfer In
6010101-149750-695500-57234-26486 Transfer In
6010101-149750-695500-57434-26486 Transfer In
Total Revenue
Expense
6010101-149750-796500-26486 Budget Equity Adjustment
Total Expense
Water and Sewer Trust Fund (57010)
Revenue
6010101-149290-665882 Planned Use of Balance
6010101-149300-665882 Planned Use of Balance
Total Revenue
Expense
6010101-149290-788001-63900 Transfer Out
6010101-149300-788001-63900 Transfer Out
Total Expense
FINANCE COMMITTEE VOTE:
Motion carried unanimously on a roll call vote with Taub and Crawford absent.
FY 2014
$115,971
$ 57,986
$ 57,985
$231,942
$231.942
$231,942
$ 57,986
$ 57,985
$115,971
$ 57,986
$ 57,985
$115.971
$ 57,986
$ 57,986
$ 57,986
$ 57 986
$ 57 985
$ 57,985
$ 57,985
$ 57,985
Pontiac Water Fund (57234)
Revenue
6010101-149030-665882 Planned Use of Balance
Total Revenue
Expense
6010101-149030-788001-63900 Transfer Out
Total Expense
Pontiac Sewer/WWTP FUND (57434)
Revenue
6010101-149030-665882 Planned Use of Balance
Total Revenue
Expense
6010101-149030-788001-63900 Transfer Out
Total Expense
Resolution #14099 April 30, 2014
Moved by Taub supported by Quarles the resolutions (with fiscal notes attached) on the Consent Agenda
be adopted (with accompanying reports being accepted).
AYES: Gershenson, Gosselin, Hatchett, Hoffman, Jackson, Long, Matis, McGillivray, Middleton,
Quarles, Runestad, Scott, Spisz, Taub, Weipert, Woodward, Zack, Bosnic, Dwyer. (19)
NAYS: None. (0)
A sufficient majority having voted in favor, the resolutions (with fiscal notes attached) on the Consent
Agenda were adopted (with accompanying reports being accepted).
HENEBY APPROVE MIS RESOLU11ON
CHIEF DEPUTY COUNTY EXECUTIVE
ACTING PURSUANT TO MCL 45.559A (7)
STATE OF MICHIGAN)
COUNTY OF OAKLAND)
I, Lisa Brown, Clerk of the County of Oakland, do hereby certify that the foregoing resolution is a true and
accurate copy of a resolution adopted by the Oakland County Board of Commissioners on April 30, 2014,
with the original record thereof now remaining in my office.
In Testimony Whereof, I have hereunto set my hand and affixed the seal of the County of Oakland at
Pontiac, Michigan this 30th day of April 2014.