Miscellaneous Resolution # 14173
BY: Commissioner Michael Spisz, District #3
RE: BOARD OF COMMISSIONERS — TRI-PARTY ROAD IMPROVEMENT PROGRAM FISCAL YEAR 2014
APPROPRIATION — CHARTER TOWNSHIP OF OAKLAND — LIMESTONE PROGRAM - PROJECT
NO. 52432
TO: Oakland County Board of Commissioners
Chairperson, Ladies and Gentlemen:
WHEREAS since the 1970s, the Oakland County Board of Commissioners has authorized the Tr-Party Road
Improvement Program to assist Oakland County's cities, villages and townships (CVTs) with the construction,
maintenance and repair of roads under the supervision, direction and control of the Road Commission for
Oakland County; and
WHEREAS Miscellaneous Resolution #09221, as amended by Miscellaneous Resolution #10045, provides that
any Oakland County appropriation in support of the Tr-Party Road Improvement Program shall be distributed only
after completion of all of the following:
1. The Road Commission for Oakland County (RCOC) and a city, village, or township (CVT) have
identified a project and the project is ready to be undertaken immediately; and
2. The RCOC has appropriated its 1/3 share of the funding for the project and transferred said
appropriation to a project account; and
3. The CVT has authorized its 1/3 share of the funding for the project and has executed a contract for
payment with the RCOC; and
4. The Commissioner(s) representing the CVT requesting the project submits a resolution authorizing
the appropriation of the County's 1/3 share of the project from the General Fund Designated Fund
Balance for Tr-Party Program. The resolution shall be approved by the Finance Committee and the
full Board; and
WHEREAS the Charter Township of Oakland, along with the RCOC has identified a project and said project is
ready to be undertaken immediately; and
WHEREAS the RCOC has appropriated its 1/3 share of the funding for the project in the Charter Township of
Oakland and said appropriation has been transferred to a project account; and
WHEREAS the Charter Township of Oakland has demonstrated that it has authorized its 1/3 share of the funding
for the project and has executed a contract for payment with the RCOC; and
WHEREAS Oakland County's one third (1/3) share of the — Fiscal Year 2014 authorized amount of Tr-Party
Road Improvement funding for Project 52432 in the Charter Township of Oakland is $20,557.
NOW THEREFORE BE IT RESOLVED that the Oakland County Board of Commissioners hereby approves the
project submitted by the Charter Township of Oakland and authorizes the release of Tr-Party Road Improvement
Program funds from the Oakland County Designated Fund Balance.
BE IT FURTHER RESOLVED additional project costs, not greater than 15% from the original agreement, which
are consistent with the project as originally approved, will be paid when invoiced and appropriated in the quarterly
forecast resolution.
BE IT FURTHER RESOLVED that additional project costs exceeding 15% of the original agreement will require a
separate Finance Committee resolution.
BE IT FURTHER RESOLVED that the Oakland County Clerk is requested to forward copies of this resolution to
the Road Commission for Oakland County, Oakland County Fiscal Services and the Charter Township of
Oakland.
BZWITCYAOAD
for OAKLAND COUNTY
U sitkA.5 OF TP svoRTATiON ExcELLECF.
;)artl of Road Commissioners
Ronald J. Fowicas
Cerotnissioner
Gregory C. Janilan
Commissioner
June 12, 2014
Ms. Karen Reilly, Clerk
Charter Township of Oakland
4393 Collins Road
Rochester, MI 48306-1670
Re: 2014 Limestone Program
Project No. 52432
Dear Ms. Reilly:
A fully signed and executed contract for the above-referenced project is
enclosed.
The agreement was approved at the regularly scheduled Board meeting of
Thursday, June 12, 2014, and subsequently signed by Dennis G. Kolar, P.E.,
Managing Director.
Please contact Thomas G. Noechel, Programming Supervisor at (248) 645-
2000 ext. 2266 to answer any questions or for additional information.
Sincerely,
Patricia Z. VVi'erzbicki
Deputy-Secretary /Clerk of the Board
Ism
Enclosure
cc: Dennis Lockhart
Tom Blust
Tom Noechel
Lynn Sonkiss
Erie S. Wilson
Commissioner
sie922.197.20,
Dennis G. Kolar, P,E.
Managing Director
Gary Pio(rowicz, PE,
Deputy Managing Director
County Highway Engineer
Clerk of the Board
31001 Lahser Road
Beverly Hills, MI 48025
248-645-2000
FAX
248-645-1349
LiteliaiMacrampioismasasnectosne.st.
www.rcocweb.org
AZINERIEWROAD
C41.7,1M55ION
100 YEARS OF TRANSPORTATION EXCELLENCE
Inter—Departmental Memorandum
PROGRAMMING DIVISION
DATE: June 2, 2014
To: Thomas G. Blust, RE., Director of Engineering
FROM: Thomas a Noechel, Programming Supervisor 1V1
SUBJECT: PROJECT NO. 52432, 2014 LIMESTONE PROGRAM
VARIOUS ROADS
LOCAL COST PARTICIPATION AGREEMENT/TRI-PARTY PROGRAM
CHARTER TOWNSHIP OF OAKLAND
Attached for your review and submission to the Board for their approval is the local cost
participation agreement with the Charter Township of Oakland for the spreading and
grading of limestone on various roads within the township. This work is expected to be
completed this summer.
The Charter Township of Oakland has elected to use the Tr-Party Program to fund the
estimated total project cost of $61,670. Our share is estimated to be $20,556 and is in
the FY14 budget.
The project is in the district of County Commissioner Michael Spisz. The agreement is
in our standard approved format, and I recommend Board approval and authorize the
Managing Director to execute the agreement on behalf of the Board.
/je
Attachments
C6-11Cur
COST PARTICIPATION AGREEMENT
2014 LIMESTONE PROGRAM
Charter Township of Oakland
Board Project No. 52432
This Agreement, made and entered into this day of (>44-- , 2014,
by and between the Board of Road Commissioners for the County of Oakland, Michigan,
hereinafter referred to as the BOARD, and the Charter Township of Oakland, hereinafter
referred to as the COMMUNITY, provides as follows:
WHEREAS, the BOARD and the COMMUNITY have agreed to program the spreading
and grading of limestone on various roads under the jurisdiction of the BOARD, as described in
Exhibit "A", attached hereto, and made a part hereof, the roads selected will be mutually agreed
upon by the BOARD and the COMMUNITY, which are hereinafter referred to as the PROJECT;
and
WHEREAS, the estimated total cost of the PROJECT is $61,670; and
WHEREAS, the PROJECT involves certain designated and approved Tr-Party Program
funding in the amount of $61,670 which amount shall be paid through equal contributions by the
BOARD, the COMMUNITY, and the Oakland County Board of Commissioners, hereinafter
referred to as the COUNTY; and
WHEREAS, the COMMUNITY and the BOARD have reached a mutual understanding
regarding the cost sharing of the PROJECT and wish to commit that understanding to writing in
this Agreement
NOW, THEREFORE, in consideration of the mutual covenants set forth herein, it is
hereby agreed between the COMMUNITY and the BOARD that:
1 The BOARD shall forthwith undertake and complete the PROJECT, as above
described, and shall perform all engineering, inspection and administration in
reference thereto.
2. The actual total cost of the PROJECT shall include total payments to the
contractor.
3. The estimated total PROJECT cost of $61,670 shall be funded in the following
order:
a.
b.
Tr-Party Program funding in the amount of $61,670.
Any PROJECT costs above the Tr-Party Program funding of $61,670 will
be funded first with any available Tr-Party Program funds. If no Tr-Party
Program funds are available, any PROJECT costs above $61,670 will be
funded 100% by the COMMUNITY.
4. Upon execution of this Agreement, the BOARD shall submit an invoice to the
COMMUNITY in the amount of $20,557 (being 100% of the COMMUNITY'S
Tr-Party contribution).
5. Upon execution of this agreement and approval by the COUNTY, the BOARD
shall submit an invoice to the COUNTY in the amount of $20,557 (being 100% of
the COUNTY'S Tr-Party contribution).
a. The invoice shall be sent to:
Lynn Sonkiss, Manager of Fiscal Services
Executive Office Building
2100 Pontiac Lake Road, Building 41 West
Waterford, MI 48328
6. Upon receipt of said invoice(s), the COMMUNITY and the COUNTY shall pay to
the BOARD the full amount thereof, within thirty (30) days of such receipt.
2014 Limestone Program - 2 -
Charter Township of Oakland
Project No. 52432
5/3012014
-41,"
IN WITNESS WHEREOF, the parties hereto have executed this Agreement the day and
date first written above,
BOARD OF ROAD COMMISSIONERS FOR THE
COUNTY OF OAKLAND
A Public Body Corporate
Managing Director
CHARTER TOWNSHIP OF OAKLAND
BY
Its
By
Its
12..,
440
2014 Limestone Program - 3 -
Charter Township of Oakland
Project No. 52432
5/30/2014
EXHIBIT A
TRI-PARTY PROGRAM
2014 Limestone Road Program
Charter Township of Oakland
Board Project No. 52432
Spreading and grading of limestone on various roads within the township.
ESTIMATED PROJECT COST
Contractor Payments $61,670
COST PARTICIPATION BREAKDOWN
COMMUNITY COUNTY BOARD TOTAL
FY2014 Tr-Party Program $20,557 $20,557 $20,556 $61,670
TOTAL SHARES $20,557 $20,557 $20,556 $61,670
2314 Limestone Program
Charter Township of Oakland
Project No. 52432
5130'2014
- 4 -
Resolution #14173 July 16, 2014
The Chairperson referred the resolution to the Finance Committee. There were no objections.