HomeMy WebLinkAboutResolutions - 2015.06.10 - 21877MISCELLANEOUS RESOLUTION # 15147
BY: Commissioner Michael Spisz, District #3
IN RE: BOARD OF COMMISSIONERS — TRI-PARTY ROAD IMPROVEMENT PROGRAM FISCAL
YEAR 2015 APPROPRIATION — TOWNSHIP OF ADDISON —2015 GRAVEL ROAD PROGRAM - NO.
52882
To the Oakland County Board of Commissioners:
Chairperson, Ladies and Gentlemen:
WHEREAS since the 1970s, the Oakland County Board of Commissioners has authorized the Tr-Party
Road Improvement Program to assist Oakland County's cities, villages and townships (CVTs) with the
construction, maintenance and repair of roads under the supervision, direction and control of the Road
Commission for Oakland County; and
WHEREAS Miscellaneous Resolution #09221, as amended by Miscellaneous Resolution #10045,
provides that any Oakland County appropriation in support of the Tr-Party Road Improvement Program
shall be distributed only after completion of all of the following:
1. The Road Commission for Oakland County (RCOC) and a city, village, or township (CVT) have
identified a project and the project is ready to be undertaken immediately; and
2. The RCOC has appropriated its 1/3 share of the funding for the project and transferred said
appropriation to a project account; and
3. The CVT has authorized its 1/3 share of the funding for the project and has executed a contract
for payment with the RCOC; and
4. The Commissioner(s) representing the CVT requesting the project submits a resolution
authorizing the appropriation of the County's 1/3 share of the project from the General Fund
Designated Fund Balance for Tr-Party Program. The resolution shall be approved by the Finance
Committee and the full Board; and
WHEREAS the Township of Addison , along with the RCOC has identified a project and said project is
ready to be undertaken immediately; and
WHEREAS the RCOC has appropriated its 1/3 share of the funding for the project in the Township of
Addison and said appropriation has been transferred to a project account; and
WHEREAS the Township of Addison has demonstrated that it has authorized its 1/3 share of the funding
for the project and has executed a contract for payment with the RCOC; and
WHEREAS Oakland County's one third (1/3) share of the Fiscal Year 2015 authorized amount of Tri-
Party Road Improvement funding for Project No. 52882 in the Township of Addison is $9,972.
NOW THEREFORE BE IT RESOLVED that the Oakland County Board of Commissioners hereby
approves the project submitted by the Township of Addison and authorizes the release of Tr-Party Road
Improvement Program funds from the Oakland County Designated Fund Balance.
BE IT FURTHER RESOLVED additional project costs, not greater than 15% from the original agreement,
which are consistent with the project as originally approved, will be paid when invoiced and appropriated
in the quarterly forecast resolution.
BE IT FURTHER RESOLVED that additional project costs exceeding 15% of the original agreement will
require a separate Finance Committee resolution.
BE IT FURTHER RESOLVED that the Oakland County Clerk is requested to forward copies of this
resolution to the Road Commission for Oakland County, Oakland County Fiscal Services and the
Township of Addison.
Chairperson, I move the adpption of the foregoing Resolution.
_Al .74...n amwis4--
District #3
Quality Life through Good Roads "We Care"
=JR AO
C 4,5:SYCPA ,
for OAKLAND COUNTY
Inter—Departmental Memorandum
PROGRAMMING DIVISION
DATE: April 24, 2015
To: Thomas G. Blust, RE., Director of Engineering
FROM: Thomas G. Noechel, Programming Supervisor790
SUBJECT: PROJECT NO. 52882, 2015 GRAVEL ROAD PROGRAM
VARIOUS ROADS
LOCAL COST PARTICIPATION AGREEMENT/TRI-PARTY PROGRAM
TOWNSHIP OF ADDISON
Attached for your review and submission to the Board for their approval is the local cost
participation agreement with the Township of Addison for the spreading of gravel and
chloride on various roads within the township. This work is expected to be completed
this summer.
The Township of Addison has elected to use the Tr-Party Program to fund the
estimated total project cost of $29,916. Our share is estimated to be $9,972 and is in
the FY15 budget.
The project is in the district of County Commissioner Michael Spisz. The agreement is
in our standard approved format, and I recommend Board approval arid authorize the
Managing Director to execute the agreement on behalf of the Board.
/je
Attachments
Recommended for Board Approval
(,-14,41 4 f /e57
Thomas G. Blust, P.E.
Director of Engineering
=ROAD COMMISSION
lot OAKLAND COUNTY
QUALITY LIFE THROUGH GOOD ROADS:
SAD COMMISSION FOR OAKLAND COUNTY
"WE CARE:' May 7, 2015
Ms. Pauline Bennett, Clerk
Township of Addison
1440 Rochester Road
Leonard, MI 48367
RE: 2015 Gravel Road Program; Project No. 52882
Dear Ms. Bennett:
A fully signed and executed agreement for the above-referenced project is
enclosed.
The agreement was approved at the regularly scheduled Board meeting of
Thursday, May 7, 2015, and subsequently signed by Dennis G. Kolar, RE.,
Managing Director.
Please contact Thomas G. Noechel, Programming Supervisor at (248) 645-
2000 ext. 2266 to answer any questions or for additional information.
Sincerely,
9ciref of Road Commissioners
Ronald J. Fowkes
Commissioner
Gregory C. Jamian
Commissioner
Eric S, Wilson
Commissioner
Dennis G. Kohr, P,E,
Managing Director
Gary Piotrowicz, P.C., P.T,O.E,
Deputy Managing Director
County Highway Engineer
Patricia Z. (Wierzbicki
Deputy-Secretary /Clerk of the Board
Ism
Clerk of the Board
Enclosure
31001 Lahser Road
Beverly Hills, Mt
48025
248-645-2000
FAX
248-645-1349
cc Finance Department
Engineering Department
Programming Division
Lynn Sonkiss
www.rcocweb.org
COST PARTICIPATION AGREEMENT
2015 GRAVEL ROAD PROGRAM
Township of Addison
Board Project No. 52882
This Agreement, made and entered into this -)-\-"\k day of , 2015,
by and between the Board of Road Commissioners for the County of Oakland, Michigan,
hereinafter referred to as the BOARD, and the Township of Addison, hereinafter referred to as
the COMMUNITY, provides as follows:
WHEREAS, the BOARD and the COMMUNITY have agreed to program the spreading of
gravel and chloride on various roads under the jurisdiction of the BOARD, as described in
Exhibit "A", attached hereto, and made a part hereof, the roads selected will be mutually agreed
upon by the BOARD and the COMMUNITY, which are hereinafter referred to as the PROJECT;
and
WHEREAS, the estimated total cost of the PROJECT is $29,916; and
WHEREAS, the PROJECT involves certain designated and approved Tri-Party Program
funding in the amount of $29,916 which amount shall be paid through equal contributions by the
BOARD, the COMMUNITY, and the Oakland County Board of Commissioners, hereinafter
referred to as the COUNTY; and
WHEREAS, the COMMUNITY and the BOARD have reached a mutual understanding
regarding the cost sharing of the PROJECT and wish to commit that understanding to writing in
this Agreement.
NOW, THEREFORE, in consideration of the mutual covenants set forth herein, it is
hereby agreed between the COMMUNITY and the BOARD that:
1. The BOARD shall forthwith undertake and complete the PROJECT, as above
described, and shall perform all engineering, inspection and administration in
reference thereto.
2. The actual total cost of the PROJECT shall include total payments to the
contractor.
3. The estimated total PROJECT cost of $29,916 shall be funded in the following
order:
a. Tr-Party Program funding in the amount of $29,916.
b. Any PROJECT costs above the Tr-Party Program funding of $29,916 will
be funded first with any available Tr-Party Program funds. If no Tr-Party
Program funds are available, any PROJECT costs above $29,916 will be
funded 100% by the COMMUNITY.
4. Upon execution of this Agreement, the BOARD shall submit an invoice to the
COMMUNITY in the amount of $9,972 (being 100% of the COMMUNITY'S
Tr-Party contribution).
5. Upon execution of this agreement and approval by the COUNTY, the BOARD
shall submit an invoice to the COUNTY in the amount of $9,972 (being 100% of
the COUNTY'S Tr-Party contribution).
a. The invoice shall be sent to:
Lynn Sonkiss, Manager of Fiscal Services
Executive Office Building
2100 Pontiac Lake Road, Building 41 West
Waterford, MI 48328
6. Upon receipt of said invoice(s), the COMMUNITY and the COUNTY shall pay to
the BOARD the full amount thereof, within thirty (30) days of such receipt.
2015 Gravel Road Pfogram
Township of Addison
Project Na 52882
2/1012016
I N WITNESS WHEREOF, the parties hereto have executed this Agreement the day and
date first written above.
BOARD OF ROAD COMMISSIONERS FOR THE
COUNTY OF OAKLAND
A Public Body Corporate
By
Its
Managing Director
By
Its
2015 Gravel Road Program
Township of Addison
Project No. 52882
211012015
EXHIBIT A
TRI-PARTY PROGRAM
2015 Gravel Road Program
Township of Addison
Board Project No. 52882
Spreading of gravel and chloride on various roads within the township.
ESTIMATED PROJECT COST
Contractor Payments
COS F PAR ICIFA HON BREAKDOWN
$29,916
COMMUNITY COUNTY BOARD TOTAL
FY2015 Tr-Party Program $9,972 $9,972 $9,972 $29,916
TOTAL SHARES $9,972 $9,972 $9,972 $29,916
2015 Gravel Road Program - 4 -
Township of Addison
Project No. 52882
2/1012015
Resolution #15147 May 21, 2015
The Chairperson referred the resolution to the Finance Committee. There were no objections.
FISCAL NOTE (MISC. *15147) June 10, 2015
BY: Finance Committee, Tom Middleton, Chairperson
IN RE: BOARD OF COMMISSIONERS — TRI-PARTY ROAD IMPROVEMENT PROGRAM FISCAL YEAR
2015 APPROPRIATION —TOWNSHIP OF ADDISON —2015 GRAVEL ROAD PROGRAM - NO. 52882
TO: The Oakland County Board of Commissioners
Chairperson, Ladies and Gentlemen:
Pursuant to Rule XII-C of this Board, the Finance Committee has reviewed the above referenced resolution
and finds:
1. On December 11,2014, the Board of Commissioners approved Miscellaneous Resolution *14295
which designated $2,000,000 in fund balance for the Tr-Party Road Improvement Program for
projects managed by the Road Commission for Oakland County (RCOC).
2. Funding of $9,972 is available in the General Fund Assigned Fund Balance for Tr-Party 2015 and
prior funding (account *383510) for project 52882.
3. This project is for the spreading of gravel and chloride on various roads within the Township of
Addison.
4. The resolution allows for additional project costs not greater than 15% from the original agreement,
which is consistent with the project as originally approved, to be paid when invoiced and appropriated
in the quarterly forecast resolution.
5. Additional project costs exceeding 15% of the original agreement will require a separate Finance
Committee resolution to appropriate the additional Oakland County share of the project costs prior to
payment.
6. The FY 2015 budget be amended as follows:
GENERAL FUND *10100
FY 2015
Revenue
9010101-196030-665882 Planned Use of Balance
Total Revenues
$9,972
$9,972
Expenditures
9010101-153010-740135 Road Commission Tr-Party $9,972
Total Expenditures
FINANCE COMMITTEE VOTE:
Motion carried unanimously on a roll call vote with Quarles absent.
Resolution #15147 June 10, 2015
Moved by Kowall supported by Jackson the resolutions (with fiscal notes attached) on the Consent
Agenda be adopted (with accompanying reports being accepted).
AYES: Dwyer, Fleming, Gershenson, Gingell, Gosselin, Hoffman, Jackson, Kowall, Long, Matis,
McGillivray, Middleton, Quarles, Scott, Spisz, Taub, Weipert, Woodward, Zack, Bowman,
Crawford. (21)
NAYS: None. (0)
A sufficient majority having voted in favor, the resolutions (with fiscal notes attached) on the Consent
Agenda were adopted (with accompanying reports being accepted).
GERALD D, POISSON
CHIP DIFPUre COUNTY EXECUTIVE
frACTPA PHrff*Atit t MCL 45.559A(7)
STATE OF MICHIGAN)
COUNTY OF OAKLAND)
I, Lisa Brown, Clerk of the County of Oakland, do hereby certify that the foregoing resolution is a true and
accurate copy of a resolution adopted by the Oakland County Board of Commissioners on June 10, 2015,
with the original record thereof now remaining in my office.
In Testimony Whereof, I have hereunto set my hand and affixed the seal of the County of Oakland at
Pontiac, Michigan this 10th day of June 2015.
Lisa Brown, Oakland County