HomeMy WebLinkAboutResolutions - 2016.04.21 - 22321Commis"sionerlirobert Gosselin
District #11 /
MISCELLANEOUS RESOLUTION #16105
BY: Commissioners Adam Kochenderfer, District #15 and Robert Gosselin, District #11
IN RE: BOARD OF COMMISSIONERS — TRI-PARTY ROAD IMPROVEMENT PROGRAM FISCAL
YEAR 2016 APPROPRIATION — CITY OF ROCHESTER HILLS — RESURFACING AND
INTERSECTION IMPROVEMENTS ON SOUTH BOULEVARD — PROJECT NO 53171
To the Oakland County Board of Commissioners:
Chairperson, Ladies and Gentlemen:
WHEREAS since the 1970s, the Oakland County Board of Commissioners has authorized the Tr-Party
Road Improvement Program to assist Oakland County's cities, villages and townships (CVTs) with the
construction, maintenance and repair of roads under the supervision, direction and control of the Road
Commission for Oakland County; and
WHEREAS Miscellaneous Resolution #09221, as amended by Miscellaneous Resolution #10045,
provides that any Oakland County appropriation in support of the Tr-Party Road Improvement Program
shall be distributed only after completion of all of the following:
1. The Road Commission for Oakland County (RCOC) and a city, village, or township (CVT) have
identified a project and the project is ready to be undertaken immediately; and
2. The RCOC has appropriated its 1/3 share of the funding for the project and transferred said
appropriation to a project account; and
3. The CVT has authorized its 1/3 share of the funding for the project and has executed a contract
for payment with the RCOC; and
4. The Commissioner(s) representing the CVT requesting the project submits a resolution
authorizing the appropriation of the County's 1/3 share of the project from the General Fund
Designated Fund Balance for Tr-Party Program. The resolution shall be approved by the Finance
Committee and the full Board; and
WHEREAS the City of Rochester Hills, along with the RCOC has identified a project and said project is
ready to be undertaken immediately; and
WHEREAS the RCOC has appropriated its 1/3 share of the funding for the project in the City of
Rochester Hills and said appropriation has been transferred to a project account; and
WHEREAS the City of Rochester Hills has demonstrated that it has authorized its 1/3 share of the funding
for the project and has executed a contract for payment with the RCOC; and
WHEREAS Oakland County's one third (1/3) share of the — Fiscal Year 2016 authorized amount of Tr-
Party Road improvement funding for Project No. 53171 in the City of Rochester Hills is $162,068.
NOW THEREFORE BE IT RESOLVED that the Oakland County Board of Commissioners hereby
approves the project submitted by the City of Rochester Hills and authorizes the release of Tr-Party Road
Improvement Program funds from the Oakland County Designated Fund Balance.
BE IT FURTHER RESOLVED additional project costs, not greater than 15% from the original agreement,
which are consistent with the project as originally approved, will be paid when invoiced and appropriated
in the quarterly forecast resolution.
BE IT FURTHER RESOLVED that additional project costs exceeding 15% of the original agreement will
require a separate Finance Committee resolution.
BE IT FURTHER RESOLVED that the Oakland County Clerk is requested to forward copies of this
resolution to the Road Commission for Oakland County, Oakland County Fiscal Services and the City of
Rochester Hills.
Chairperson, I move the adoption of the foregoing Resolution.
'Thomas G. Biust, P.E.
Director of Engineering
Quality Life through Good Roads "We Care"
t=1=1=71740#427
Csaisirliff-SIWCIPAf
W/J
04/07/16
15A
for OAKLAND COUNTY
Inter—Departmental Memorandum
PROGRAMMING DIVISION
DATE: March 30, 2016
4,Nt To: Thomas G. Blust, P.E., Director of Engineering
FROM: Thomas G. Noechel, Programming Supervisol
SUBJECT: PROJECT NO. 53171, SOUTH BOULEVARD
EAST OF LIVERNOIS ROAD TO EAST OF ROCHESTER ROAD
LOCAL COST PARTICIPATION AGREEMENT/TRI-PARTY PROGRAM
CITY OF ROCHESTER HILLS
Attached for your review and submission to the Board for their approval is the local cost
participation agreement with the City of Rochester Hills for the resurfacing and
intersection improvements on South Boulevard from east of Livernois Road to east of
Rochester Road. Construction on this project is expected to begin this summer.
The estimated total cost is $3,475,000 and will be funded with a contribution of
$375,864 from the City of Rochester Hills, $1,009,000 from the City of Troy, $162,068
from the County of Oakland, and $1,928,068 from the Board. This agreement is with
the City of Rochester Hills which includes the use of Tr-Party Program funds.
The project is in the district of County Commissioners Robert Gosselin and Jeff Matis.
The agreement is in our standard approved format, and I recommend Board approval
and authorize the Managing Director to execute the agreement on behalf of the Board.
/je
Attachments
Recommended for Board Approval
=ROAD CONNISSION for OAKLAND COUNTY QUALITY LIFE THROUGH GOOD ROADS; :GAD COMMISSION FOR OAKLAND COUNTY WE CARE." April 7, 2016 4oard of Road Commissioners Ronald .1. Fowkes Commissioner Gregory C. Jamian Commissioner Eric S. Wilson Commissioner Dennis G. Kolar, P.E. Managing Director Gary Piotrowicz, P.E., P. T. 0.E. Deputy Managing Director County Highway Engineer Clerk of the Board 31001 Lahser Road Beverly Hills, MI 48025 248-645-2000 FAX 248-645-0452 TDD 248-645-9923 www.rcocweb.org Ms. Tina Barton, Clerk City of Rochester Hills 1000 Rochester Hills Drive Rochester Hills, MI 48309-3033 Re: SOUTH BOULEVARD EAST OF LIVERNOIS ROAD TO EAST OF ROCHESTER ROAD PROJECT NO. 53171 Dear Ms. Barton: A fully signed and executed agreement for the above mentioned project is enclosed. The agreement was approved and subsequently signed by Dennis G. Kolar, P.E., Managing Director at the regularly scheduled Board meeting of Thursday, April 7, 2016. Please contact Thomas G. Noechel, Programming Supervisor at (248) 645-2000 ext. 2266 to answer questions or for additional information. Sincerely, 4cunnci44411,QC)...__ Shannon J. Miller Deputy-Secretary /Clerk of the Board Ism Enclosure cc: Finance Department Engineering Department Programming Division Lynn Sonkiss, Oakland County
COST PARTICIPATION AGREEMENT
CONSTRUCTION
South Boulevard
East of Livernois Road to East of Rochester Road
City of Rochester Hills
Board Project No. 53171
This Agreement, made and entered into this la" day of Apy-'1 t , 2016,
by and between the Board of County Road Commissioners of the County of Oakland, Michigan,
hereinafter referred to as the BOARD, and the City of Rochester Hills, hereinafter referred to as
ROCHESTER HILLS, provides as follows:
WHEREAS, the BOARD, ROCHESTER HILLS, and the City of Troy, hereinafter referred
to as TROY, have programmed the resurfacing and intersection improvements on South
Boulevard from east of Livernois Road to east of Rochester Road, as described in Exhibit "A",
attached hereto, and made a part hereof, which improvements involve roads under the
jurisdiction of the BOARD and within ROCHESTER HILLS and TROY, which improvements are
hereinafter referred to as the PROJECT; and
WHEREAS, for purposes of identification and funding, the PROJECT has been divided
into four segments, as follows:
Part A: Resurfacing on South Boulevard from east of Livernois Road to east of
Rochester Road including the reconstruction of the Rochester Road at South
Boulevard intersection.
Part B: Right-turn lane on eastbound South Boulevard.
Part C: Traffic signal on South Boulevard at Rochester Road.
Part D: Concrete repair on Rochester Road north of South Boulevard.
WHEREAS, the estimated total cost of the PROJECT is $3,475,000; and
WHEREAS, ROCHESTER HILLS' share of said LOCAL SHARE involves certain
designated and approved Tr-Party Program funding in the amount of $486,204, which shall be
paid through equal contributions by the BOARD, ROCHESTER HILLS, and the Oakland County Board of Commissioners, hereinafter referred to as the COUNTY; and WHEREAS, all the parties hereto have reached a mutual understanding regarding the cost sharing for the PROJECT and wish to commit that understanding to writing in this Agreement. NOW, THEREFORE, in consideration of the mutual covenants set forth herein and in conformity with applicable law, it is hereby agreed between ROCHESTER HILLS and the BOARD that: 1 ROCHESTER HILLS and TROY approve of the PROJECT, declare its public necessity, and authorizes the BOARD to perform or cause to be performed, and complete the PROJECT along with all administration in reference thereto, 2. The PROJECT shall include preliminary engineering, right-of-way acquisition, construction engineering, and total payments to the contractor. 3. The estimated total PROJECT cost is $3,475,000 and shall be funded as follows: PART A — Resurfacing on South Boulevard/Reconstruction of Rochester Road at South Boulevard intersection: All preliminary engineering costs and any overages associated with PART A of the PROJECT, estimated in the amount of $200,100, shall be funded entirely by TROY. All construction engineering costs and any overages associated with PART A of the PROJECT, estimated in the amount of $300,150, shall be funded entirely by the BOARD. All construction costs and any overages associated with PART A of the PROJECT, estimated in the amount of $2,001,000, shall be shared equally between the BOARD, ROCHESTER HILLS, and TROY. PART B — Right-turn lane on eastbound South Boulevard: All preliminary engineering costs and any averages associated with PART B of the PROJECT, estimated in the amount of $9,900, shall be funded entirely by TROY. All right-of-way acquisition costs and any overages associated with PART B of the PROJECT, estimated in the amount South Boulevard - 2 - City of Rochester Hills Project No. 53171 2/26/2016
of $100,000, shall be shared equally between the BOARD and TROY. All construction
engineering costs and any overages associated with PART B of the PROJECT,
estimated in the amount of $14,850, shall be funded entirely by the BOARD. All
construction costs and any overages associated with PART B of the PROJECT,
estimated in the amount of $99,000, shall be shared equally between the BOARD,
ROCHESTER HILLS, and TROY.
PART C — Traffic signal at South Boulevard at Rochester Road: All preliminary
engineering costs and any overages associated with PART C of the PROJECT,
estimated in the amount of $14,000, shall be funded entirely by TROY. All construction
engineering costs and any overages associated with PART C of the PROJECT,
estimated in the amount of $21,000, shall be funded entirely by the BOARD. All
construction costs and any overages associated with PART C of the PROJECT,
estimated in the amount of $140,000, shall be shared on a 75%/25% ratio between the
BOARD and TROY, respectively.
PART D — Concrete repair on Rochester Road north of South Boulevard: All
preliminary engineering, construction engineering (estimated in the amount of $75,000),
and contractor payments associated (estimated in the amount of $500,000) with
PART D of the PROJECT shall be funded entirely by the BOARD including any
overages.
4. ROCHESTER HILLS estimated LOCAL SHARE is $700,000 and shall be funded in the
following order:
a. Tr-Party Program funding in the amount of $486,204.
b. ROCHESTER HILLS shall contribute an additional $213,796.
5. Upon execution of this agreement, the BOARD shall submit an invoice to ROCHESTER
HILLS in the amount of $375,864 (being 100% of ROCHESTER HILLS' Tr-Party
contribution of $162,068 for construction and 100% of ROCHESTER HILLS' estimated
additional contribution of $213,796 for construction).
South Boulevard -.3-
City of Rochester Hills
Project No. 53171
2/26/2016
6. Upon execution of this agreement and approval by the COUNTY, the BOARD shall submit an invoice to the COUNTY in the amount of $162,068 (being 100% of the COUNTY'S Tr-Party contribution). a. The invoice shall be sent to: Lynn Sonkiss, Manager of Fiscal Services Executive Office Building 2100 Pontiac Lake Road, Building 41 West Waterford, MI 48328 7. Upon receipt of said invoice(s), ROCHESTER HILLS and the COUNTY shall pay to the BOARD the full amount thereof, within thirty (30) days of such receipt. 8. The BOARD shall execute a separate Cost Participation Agreement with TROY, for their share of the estimated PROJECT cost. South Boulevard - 4 - City of Rochester Hills Project No. 53171 2126/2016
IN WITNESS WHEREOF, the parties hereto have executed this Agreement the day and
date first written above,
BOARD OF ROAD COMMISSIONERS FOR THE
COUNTY OF OAKLAND
A Public Body Corporate
By J
Its Managing Director
South Boulevard - 5 -
City of Rochester Hills
Project No. 53171
2/26/2018
EXHIBIT A TRI-PARTY PROGRAM South Boulevard East of Livernois Road to East of Rochester Road City of Rochester Hills Project No. 53171 Resurfacing of South Boulevard from east of Livernois Road to east of Rochester Road including the reconstruction of the Rochester Road at South Boulevard intersection, the addition of a right-turn lane on eastbound South Boulevard at Rochester Road, new traffic signal at South Boulevard at Rochester Road, and concrete pavement repair on Rochester Road north of South Boulevard. ESTIMATED PROJECT COST Preliminary Engineering* Right-of-Way Acquisition Construction Engineering** Construction TOTAL ESTIMATED COST Part A Part fl Part C Part D Total $200,100 $9,900 $14,000 RCOC $224,000 $0 $100,000 $0 $0 $100,000 $300,150 $14,850 $21,000 $75,000 $411,000 $2,001,000 $99,000 $140,000 $500,000 $2,740,000 $2,501,250 $223,750 $175,000 $575,000 $3,475,000 * PE for Part A, Part B, and Part C funded and administered by TROY (not to be invoiced as part of project). **CE for Part A, Part B, Part C, and Part D funded and administered by the BOARD (not to be invoiced as part of project). DISTRIBUTION OF PROJECT COSTS Part A Part B Part C Part D Total I Board - Right of Way - Construction Engineering - Construction BOARD TOTAL $0 $300,150 $667,000 $967,150 $50,000 $14,850 $33,000 $97,850 $0 $21,000 $105,000 $126,000 $0 $50,000 $75,000 $411,000 $500,000 $1,305,000 $575,000 $1,766,000 , Rochester Hills - Construction ROCHESTER HILLS TOTAL $667,000 $33,000 $667,000 $33,000 $0 $0 $700,000 $0 $700,000 $0 Troy - Preliminary Engineering - Right of Way - Construction TROY TOTAL TOTAL ESTIMATED COST $200,100 $0 $667,000 $867,100 $9,900 $50,000 $33,000 $92,900 $14,000 $0 $35,000 $49,000 RCOC $224,000 $0 $50,000 $0 $735,000 $0 $1,009,000 $2,501,250 $223,750 $175,000 $575,000 $3,475,000 [ COST PARTICIPATION BREAKDOWN FY2011 Tr-Party Program FY2016 Tr-Party Program Contribution TOTAL SHARES Rochester Hills $2,708 $159,360 $213,796 $375,864 Troy Board $0 $2,709 $0 $159,359 $1,009,000 $1,766,000 $1,009,000 $1,928,068 County Total $2,708 $8,125 $159,360 $478,079 $0 $2,988,796 $162,068 $3,475,000
March 15, 2016
MICHIGAN
File Number: 2016-0094
Rochester Hills
Certified Copy
Purchase: RES0079-2016
1000 Rochester Hills Dr
Rochester Hills, MI 48309
(248) 656-4600
Horne Page:
www.rochesterhills.org
Enactment Number: RES0079-2016
Request for Purchase Authorization - DPS/ENG: Cost Participation Agreement approval between the
City of Rochester Hills and Board of Road Commissioners for the County of Oakland for resurfacing
and intersection improvements on South Boulevard from east of Livernois Road to east of Rochester
Road in the amount not-to-exceed $375,864.00; Road Commission for Oakland County, Beverly Hills,
MI
Resolved, that the Rochester Hills City Council hereby approves the Cost Participation Agreement between the City
of Rochester Hills and the Board of Road Commissioners for the County of Oakland for the resurfacing and
intersection improvements on South Boulevard from east of Livernois Road to east of Rochester Road in the
amount not-to-exceed $375,864.00 and further authorizes the Mayor to execute an agreement on behalf of the City
Tina Barton, City Clerk, certify that this is a true copy of RES0079-2016 passed at the
Rochester Hills City Council Regular Meeting held on 3/1412016 by the following vote:
Moved by Susan M. Bowyer, Seconded by Thomas W. Wiggins
Aye: Bowyer, Kubicina, Morita, Tisdel and Wiggins
Absent: Brown and Hetrick
Tina Barton, MMC, City Clerk Date Certified
Rochester Hills Page 1 Printed on 3/15/2016
Resolution #16105 April 21, 2016
The Chairperson referred the resolution to the Finance Committee. There were no objections.