HomeMy WebLinkAboutResolutions - 2018.04.19 - 23402MISCELLANEOUS RESOLUTION # 18112
BY: Commissioner Bill Dwyer, District #14
IN RE: BOARD OF COMMISSIONERS — TRI-PARTY ROAD IMPROVEMENT PROGRAM FISCAL YEAR
2018 APPROPRIATION — VILLAGE OF BEVERLY HILLS — RESURFACING OF GREENFIELD ROAD
FROM 13 MILE ROAD TO 14 MILE ROAD — PROJECT NO. 54301
To the Oakland County Board of Commissioners:
Chairperson, Ladies and Gentlemen:
WHEREAS since the 1970s, the Oakland County Board of Commissioners has authorized the Tr-Party
Road Improvement Program to assist Oakland County's cities, villages and townships (CVTs) with the
construction, maintenance and repair of roads under the supervision, direction and control of the Road
Commission for Oakland County; and
WHEREAS Miscellaneous Resolution #09221, as amended by Miscellaneous Resolution #10045, provides
that any Oakland County appropriation in support of the Tr-Party Road Improvement Program shall be
distributed only after completion of all of the following:
1. The Road Commission for Oakland County (RCOC) and a city, village, or township (CVT) have
identified a project and the project is ready to be undertaken immediately; and
2. The RCOC has appropriated its 1/3 share of the funding for the project and transferred said
appropriation to a project account; and
3. The CVT has authorized its 1/3 share of the funding for the project and has executed a contract for
payment with the RCOC; and
4. The Commissioner(s) representing the CVT requesting the project submits a resolution authorizing
the appropriation of the County's 1/3 share of the project from the General Fund Assigned Fund
Balance for Tr-Party Program. The resolution shall be approved by the Finance Committee and
the full Board; and
WHEREAS the Village of Beverly Hills, along with the RCOC has identified a project and said project is
ready to be undertaken immediately; and
WHEREAS the RCOC has appropriated its 1/3 share of the funding for the project in the Village of Beverly
Hills and said appropriation has been transferred to a project account; and
WHEREAS the Village of Beverly Hills has demonstrated that it has authorized its 1/3 share of the funding
for the project and has executed a contract for payment with the RCOC; and
WHEREAS Oakland County's one third (1/3) share of the — Fiscal Year 2018 authorized amount of Tr-
Party Road Improvement funding for Project No. 54301 in the Village of Beverly Hills is $30,762.
NOW THEREFORE BE IT RESOLVED that the Oakland County Board of Commissioners hereby approves
the project submitted by the Village of Beverly Hills and authorizes the release of Tr-Party Road
Improvement Program funds from the Oakland County Assigned Fund Balance.
BE IT FURTHER RESOLVED additional project costs, not greater than 15% from the original agreement,
which are consistent with the project as originally approved, will be paid when invoiced and appropriated in
the quarterly forecast resolution.
BE IT FURTHER RESOLVED that additional project costs exceeding 15% of the original agreement will
require a separate Finance Committee resolution.
BE IT FURTHER RESOLVED that the Oakland County Clerk is requested to forward copies of this
resolution to the Road Commission for Oakland County, Oakland County Fiscal Services and the Village
of Beverly Hills.
Chairperson, I move the adoption of the foregoing Resolution.
A/,
Commissioner Bill Dwyer
District #14
Quality Life through Good Roads "We Care"
=1=7,1140,01
CCW1 107:5370Af
-179-- 19G
04/12/18
for OAKLAND COUNTY
Inter—Departmental Memorandum
PROGRAMMING DIVISION
DATE: March 23, 2018
To: Thomas G. Blust, RE., Director of Engineering
FROM: Thomas G. Noechel, Programming Supervisor 7-4111
SUBJECT: PROJECT NO. 54301, GREENFIELD ROAD
13 MILE ROAD TO 14 MILE ROAD
LOCAL COST PARTICIPATION AGREEMENT/TRI-PARTY PROGRAM
VILLAGE OF BEVERLY HILLS
Attached for your review and submission to the Board for their approval is the local cost
participation agreement with the Village of Beverly Hills for the resurfacing of
Greenfield Road from 13 Mile Road to 14 Mile Road. Construction on this project is
expected to be completed this year.
The estimated cost of $240,000 will be shared equally between the City of Royal Oak and
the Village of Beverly Hills. The Village of Beverly Hills has elected to use the Tri-Party
Program along with a contribution of $27,713 to fund their one-half share of $120,000.
Our total estimated share is $70,763 and is in the FY18 budget.
The project is in the district of County Commissioners Bill Dwyer and Dave Woodward.
The agreement is in our standard approved format, and I recommend Board approval and
authorize the Managing Director to execute the agreement on behalf of the Board.
/je
Attachments
Recommended for Board Approval
Thomas G. Blust, P.E.
Director of Engineering
LC1/1_
Sincerely,
aA n
1:=ROAD
COMMISSION
for OAKLAND COUNTY
QUALITY LIFE THROUGH GOOD ROADS:
:OAD COMMISSION FOR OAKLAND COUNTY
"WE CARE."
April 12, 2018
3oard of Road Commissioners
Ronald J. Fawkes
Commissioner
Gregory C. Jamian
Commissioner
Eric S. Wilson
Commissioner
Dennis G. Kolar, RE
Managing Director
Gary Piotrowiez, P.E., P. TOE.
Deputy Managing Director
County Highway Engineer
Clerk of the Board
31001 Lahser Road
Beverly Hills, MI
48025
248-845-2000
FAX
248-645-0452
Tin
248-645-9923
www.rcocweb.org
Ms. Melanie Halas, Clerk
City of Royal Oak
211 Williams Street
Royal Oak, MI 48068-0064
Re: Project No. 54301, Greenfield Road
13 Mile Road to 14 Mile Road
Dear Ms. Halas:
A fully signed and executed agreement for the above-mentioned project is
enclosed.
The agreement was approved and subsequently signed by Dennis G.
Kolar, P.E., Managing Director at the regularly scheduled Board meeting of
April 12, 2018.
Please contact Thomas G. Noechel, Programming Supervisor at (248)
645-2000 ext. 2266 to answer questions or for additional information.
ihannon J. Miker
Deputy-Secretary /Clerk of the Board
Ism
Enclosure
cc: Finance Department
Engineering Department
Programming Division
Lynn Sonkiss, Oakland County
COST PARTICIPATION AGREEMENT
CONSTRUCTION
Greenfield Road
13 Mile Road to 14 Mile Road
Village of Beverly Hills
Board Project No. 54301
This Agreement, made and entered into this 12th day of April , 2018, by
and between the Board of County Road Commissioners of the County of Oakland, Michigan,
hereinafter referred to as the BOARD, and the Village of Beverly Hills, hereinafter referred to as
BEVERLY HILLS, provides as follows:
WHEREAS, the BOARD, BEVERLY HILLS, and the City of Royal Oak, hereinafter referred
to as ROYAL OAK, have programmed the resurfacing of Greenfield Road from 13 Mile Road to
14 Mile Road, as described in Exhibit "A", attached hereto, and made a part hereof, which
improvements involve roads under the jurisdiction of the BOARD and within ROYAL OAK and
BEVERLY HILLS, which improvements are hereinafter referred to as the PROJECT; and
WHEREAS, the estimated total cost of the PROJECT is $240,000; and
WHEREAS, BEVERLY HILLS' share of said LOCAL SHARE involves certain designated
and approved Tr-Party Program funding in the amount of $92,287, which shall be paid through
equal contributions by the BOARD, BEVERLY HILLS, and the Oakland County Board of
Commissioners, hereinafter referred to as the COUNTY; and
WHEREAS, all the parties hereto have reached a mutual understanding regarding the cost
sharing for the PROJECT and wish to commit that understanding to writing in this Agreement.
NOW, THEREFORE, in consideration of the mutual covenants set forth herein and in
conformity with applicable law, it is hereby agreed between BEVERLY HILLS and the BOARD
that:
1. ROYAL OAK and BEVERLY HILLS approve of the PROJECT, declare its public
necessity, and authorizes the BOARD to perform or cause to be performed, and complete
the PROJECT along with all administration in reference thereto.
2. The PROJECT shall include total payments to the contractor. Any costs incurred by
RCOC prior to this agreement date shall be allowable.
3. The estimated total PROJECT cost is $240,000 and shall be allocated to 3.a. and 3.b.
simultaneously:
a. ROYAL OAK has agreed to contribute $120,000 and will fund their share from the
Tr-Party Program.
b. BEVERLY HILLS has agreed to contribute $120,000 and will fund their share from
the Tr-Party Program along with an additional contribution of $27,713.
c. Any PROJECT costs above ROYAL OAK'S funding of $120,000 and BEVERLY
HILLS' funding of $120,000 will be funded first with any available Tr-Party Program
funds. If no Tr-Party Program funds are available, any PROJECT costs above
$240,000 will be shared equally between ROYAL OAK and BEVERLY HILLS.
4. Upon execution of this agreement, the BOARD shall submit an invoice to BEVERLY
HILLS in the amount of $58,475 (being 100% of BEVERLY HILLS' Tr-Party contribution
and their additional contribution).
5. Upon execution of this agreement and approval by the COUNTY, the BOARD shall
submit an invoice to the COUNTY in the amount of $30,762 (being 100% of the
COUNTY'S Tr-Party contribution).
a, The invoice shall be sent to:
Lynn Sonkiss, Manager of Fiscal Services
Executive Office Building
2100 Pontiac Lake Road, Building 41 West
Waterford, MI 48328
6. Upon receipt of said invoice(s), BEVERLY HILLS and the COUNTY shall pay to the
BOARD the full amount thereof, within thirty (30) days of such receipt.
7. The BOARD shall execute a separate Cost Participation Agreement with ROYAL OAK,
for their share of the estimated PROJECT cost.
Greenfield Road - 2 -
Village of Beverly Hills
Project No. 54301
3/9/2018
IN WITNESS WHEREOF, the parties hereto have executed this Agreement the day and
date first written above.
BOARD OF ROAD COMMISSIONERS OF THE
COUNTY OF OAKLAND
A Public Body Corporate
By
Its
Managing Director
VILLAGE OF BEVERLY HILLS
By 6lL. t , 14, 1, /Z
Its \,frilLt-A16,:i:
Greenfield Road
Village of Beverly Hills
Project No. 54301
3/9/2018
EXHIBIT A
TRI-PARTY PROGRAM
Greenfield Road
13 Mile Road to 14 Mile Road
Village of Beverly Hills
Board Project No. 54301
Resurfacing of Greenfield Road from 13 Mile Road to 14 Mile Road.
[
ESTIMATED PROJECT COST
Contractor Payments $240,000
COST PARTICIPATION BREAKDOWN
ROYAL OAK BEVERLY
HILLS COUNTY BOARD TOTAL
FY2009 Tri-Party Program $8,316 $0 $8,316 $8,315 $24,947
FY2010 Tr-Party Program $10,430 $0 $10,430 $10,431 $31,291
FY2011 Tr-Party Program $10,630 $0 $10,630 $10,629 $31,889
FY2014 Tr-Party Program $10,624 $0 $10,624 $10,625 $31,873
FY2016 Tri-Party Program $0 $10,582 $10,583 $10,583 $31,748
FY2017 Tr-Party Program $0 $10,419 $10,418 $10,419 $31,256
FY2018 Tr-Party Program $0 $9,761 $9,761 $9,761 $29,283
Contribution $0 $27,713 $0 $0 $27,713
TOTAL SHARES $40,000 $58,475 $70,762 $70,763 $240,000
Greenfield Road -4-
Village of Beverly Hills
Project No. 54301
3/9/2018
Resolution #18112 April 19, 2018
The Chairperson referred the resolution to the Finance Committee. There were no objections.