HomeMy WebLinkAboutResolutions - 2018.04.19 - 23422MISCELLANEOUS RESOLUTION #18126
BY: Commissioner Eileen KowaII, District #6
IN RE: BOARD OF COMMISSIONERS — TRI-PARTY ROAD IMPROVEMENT PROGRAM FISCAL YEAR
2018 APPROPRIATION — CHARTER TOWNSHIP OF WHITE LAKE — 2018 GRAVEL ROAD PROGRAM
— PROJECT NO. 54242
To the Oakland County Board of Commissioners:
Chairperson, Ladies and Gentlemen:
WHEREAS since the 1970s, the Oakland County Board of Commissioners has authorized the Tr-Party
Road Improvement Program to assist Oakland County's cities, villages and townships (CVTs) with the
construction, maintenance and repair of roads under the supervision, direction and control of the Road
Commission for Oakland County; and
WHEREAS Miscellaneous Resolution #09221, as amended by Miscellaneous Resolution #10045, provides
that any Oakland County appropriation in support of the Tr-Party Road Improvement Program shall be
distributed only after completion of all of the following:
1. The Road Commission for Oakland County (RCOC) and a city, village, or township (CVT) have
identified a project and the project is ready to be undertaken immediately; and
2. The RCOC has appropriated its 1/3 share of the funding for the project and transferred said
appropriation to a project account; and
3. The CVT has authorized its 1/3 share of the funding for the project and has executed a contract for
payment with the RCOC; and
4. The Commissioner(s) representing the CVT requesting the project submits a resolution authorizing
the appropriation of the County's 1/3 share of the project from the General Fund Assigned Fund
Balance for Tr-Party Program. The resolution shall be approved by the Finance Committee and
the full Board; and
WHEREAS the Charter Township of White Lake, along with the RCOC has identified a project and said
project is ready to be undertaken immediately; and
WHEREAS the RCOC has appropriated its 113 share of the funding for the project in the Charter Township
of White Lake and said appropriation has been transferred to a project account; and
WHEREAS the Charter Township of White Lake has demonstrated that it has authorized its 1/3 share of
the funding for the project and has executed a contract for payment with the RCOC; and
WHEREAS Oakland County's one third (1/3) share of the — Fiscal Year 2018 authorized amount of Tr-
Party Road Improvement funding for Project No. 54242 in the Charter Township of White Lake is $58,847.
NOW THEREFORE BE IT RESOLVED that the Oakland County Board of Commissioners hereby approves
the project submitted by the Charter Township of White Lake and authorizes the release of Tr-Party Road
Improvement Program funds from the Oakland County Assigned Fund Balance.
BE IT FURTHER RESOLVED additional project costs, not greater than 15% from the original agreement,
which are consistent with the project as originally approved, will be paid when invoiced and appropriated in
the quarterly forecast resolution.
BE IT FURTHER RESOLVED that additional project costs exceeding 15% of the original agreement will
require a separate Finance Committee resolution.
BE IT FURTHER RESOLVED that the Oakland County Clerk is requested to forward copies of this
resolution to the Road Commission for Oakland County, Oakland County Fiscal Services and the Charter
Township of White Lake.
Chairperson, I move the adoption of the foregoing Resolution.
/CdTaioner Eileen Kowa
( District #6
Thomas G. Blust, P.E.
Director of Engineering
Quality Life through Good Roads "We Care"
AC=Prir adti ACP CCP AWLS ZCIP A if
3737- 19D
04/12/18
for OAKLAND COUNTY
Inter—Departmental Memorandum
PROGRAMMING DIVISION
DATE: March 22, 2018
To: Thomas G. Blust, RE., Director of Engineering
FROM: Thomas G. Noechel, Programming Supervisor Ti'
SUBJECT: PROJECT NO. 54242, 2018 GRAVEL ROAD PROGRAM
VARIOUS ROADS
LOCAL COST PARTICIPATION AGREEMENT/TRI-PARTY PROGRAM
CHARTER TOWNSHIP OF WHITE LAKE
Attached for your review and submission to the Board for their approval is the local cost
participation agreement with the Charter Township of White Lake for the spreading of
gravel and chloride on various roads within the township. This work is expected to be
completed this summer.
The Charter Township of White Lake has elected to use the Tr-Party Program to fund the
estimated total project cost of $176,542. Our share is estimated to be $58,848 and is in
the FY18 budget.
The project is in the district of County Commissioner Eileen Kowall. The agreement is in
our standard approved format, and I recommend Board approval and authorize the
Managing Director to execute the agreement on behalf of the Board.
/je
Attachments
nA
-olg-1
Clerk of the Board
31001 Lahser Road
Beverly Hills, Nil
48025
248-645-2000
hannon J. MiDer
Deputy-Secretary /Clerk of the Board
Ism
Enclosure
=ROAD
COMMISSION
for OAKLAND COUNTY
QUALITY LIPRITIROUON GOOD ROADS:
:OAD COMMISSION FOR OAKLAND COUNTY
"WE CARE."
April 12, 2018
Mr. Terry LiIley, Clerk
Charter Township of White Lake
7525 Highland Road
White Lake, Ml 48383-2900
Re: Project No. 54242, 2018 Gravel Road Program
Various Roads
Dear Mr. LiIley:
A fully signed and executed agreement for the above-mentioned project is
enclosed.
The agreement was approved and subsequently signed by Dennis G.
Kolar, RE., Managing Director at the regularly scheduled Board meeting of
April 12, 2018.
3oard of Road Commissioners
Ronald Fawkes
Commissioner
Gregory C. Jam/an
Commissioner
Eric S. Wilson
Commissioner
Dennis G. Kolar, P.E.
Managing Director
Gary Piotrowicz, P.T.O.E
Deputy Managing Director
County Highway Engineer
Please contact Thomas G. Noechel, Programming Supervisor at (248)
645-2000 ext. 2266 to answer questions or for additional information.
FAX
248-645-0452
TOO
248-645-9923
www.rcocweb.org
cc: Finance Department
Engineering Department
Programming Division
Lynn Sonkiss, Oakland County
COST PARTICIPATION AGREEMENT
2018 GRAVEL ROAD PROGRAM
Charter Township of White Lake
Board Project No. 54242
This Agreement, made and entered into this 12th day of April , 2018, by
and between the Board of County Road Commissioners of the County of Oakland, Michigan,
hereinafter referred to as the BOARD, and the Charter Township of White Lake, hereinafter
referred to as the COMMUNITY, provides as follows:
WHEREAS, the BOARD and the COMMUNITY have agreed to program the spreading of
gravel and chloride on various roads under the jurisdiction of the BOARD, as described in Exhibit
"A", attached hereto, and made a part hereof, the roads selected will be mutually agreed upon by
the BOARD and the COMMUNITY, which are hereinafter referred to as the PROJECT; and
WHEREAS, the estimated total cost of the PROJECT is $176,542; and
WHEREAS, the PROJECT involves certain designated and approved Tr-Party Program
funding in the amount of $176,542 which amount shall be paid through equal contributions by the
BOARD, the COMMUNITY, and the Oakland County Board of Commissioners, hereinafter
referred to as the COUNTY; and
WHEREAS, the COMMUNITY and the BOARD have reached a mutual understanding
regarding the cost sharing of the PROJECT and wish to commit that understanding to writing in
this Agreement.
NOW, THEREFORE, in consideration of the mutual covenants set forth herein, it is hereby
agreed between the COMMUNITY and the BOARD that:
1. The BOARD shall forthwith undertake and complete the PROJECT, as above
described, and shall perform all engineering, inspection and administration in
reference thereto.
2. The actual total cost of the PROJECT shall include total payments to the contractor.
Any costs incurred by RCOC prior to this agreement date shall be allowable.
3. The estimated total PROJECT cost of $176,542 shall be funded and invoiced in
the following order:
a. Tr-Party Program funding in the amount of $176,542.
b. Any PROJECT costs above the Tr-Party Program funding of $176,542 will
be funded first with any available Tr-Party Program funds. If no Tr-Party
Program funds are available, any PROJECT costs above $176,542 will be
funded 100% by the COMMUNITY.
4. Upon execution of this Agreement, the BOARD shall submit an invoice to the
COMMUNITY in the amount of $58,847 (being 100% of the COMMUNITY'S
Tr-Party contribution).
5. Upon execution of this agreement and approval by the COUNTY, the BOARD shall
submit an invoice to the COUNTY in the amount of $58,847 (being 100% of the
COUNTY'S Tr-Party contribution).
a. The invoice shall be sent to:
Lynn Sonkiss, Manager of Fiscal Services
Executive Office Building
2100 Pontiac Lake Road, Building 41 West
Waterford, MI 48328
6. Upon receipt of said invoice(s), the COMMUNITY and the COUNTY shall pay to the
BOARD the full amount thereof, within thirty (30) days of such receipt.
2018 Gravel Road Program
White Lake Twp,
Project No. 54242
3/1/2018
IN WITNESS WHEREOF, the parties hereto have executed this Agreement the day and
date first written above.
BOARD OF ROAD COMMISSIONERS OF THE
COUNTY OF OAKLAND
A Public Body Corporate
By JaL_
Its Managing Director
CHARTER TOWNSHIP OF WHITE LAKE
Its 'C r
2018 Gravel Road Program
Mite Lake NI
Project No. 54242
3/112018
- 3
EXHIBIT A
TRI-PARTY PROGRAM
2018 Gravel Road Program
Charter Township of White Lake
Board Project No. 54242
Spreading of gravel and chloride on various roads within the township.
ESTIMATED PROJECT COST
Contractor Payments $176,542
COST PARTICIPATION BREAKDOWN
COMMUNITY COUNTY BOARD TOTAL
FY2016 Tri-Party Program $315 $315 $316 $946
FY2018 Tr-Party Program $58,532 $58,532 $58,532 $175,596
TOTAL SHARES $58,847 _ $58,847 $58,848 $176,542
2018 Gravel Road Program
White Lake Twp,
Pitied No. 54242
3/1/2018
- 4 -
Resolution #18126 April 19, 2018
The Chairperson referred the resolution to the Finance Committee. There were no objections.