HomeMy WebLinkAboutResolutions - 2000.06.15 - 26085MISCELLANEOUS RESOLUTION #00155 June 15, 2000
BY: FINANCE COMMITTEE, SUE ANN DOUGLAS, CHAIRPERSON
IN RE: BOARD OF COMMISSIONERS - PROPOSED LYON TOWNSHIP DOWNTOWN DEVELOPMENT
AUTHORITY - TAX CAPTURE
TO THE OAKLAND COUNTY BOARD OF COMMISSIONERS
Chairperson, Ladies and Gentlemen:
WHEREAS the Oakland County Board of Commissioners strongly supports the
economic growth of Oakland County; and
WHEREAS on of the tools used to promote this economic growth is Tax
Increment Financing in the form of Downtown Development Authorities (DDAs),
Tax Increment Finance Authorities (TIFAs) and Local Development Finance
Authorities (LFDAs); and
WHEREAS amendments to the Tax Increment Financing programs were adopted
in 1994 by the State Legislature, providing the County with the option to
exempt itself from participating in these authorities; and
WHEREAS in order to review requests from the County's cities, villages
and townships to establish DDAs, TIFAs and LFDAs, the Board of Commissioners,
pursuant to Miscellaneous Resolution #99010, established the Tax Increment
Financing (TIF) District Review Policy Ad Hoc Committee to evaluate and
recommend to the Finance Committee on the County's participation in these
proposed authorities; and
WHEREAS Lyon Township has submitted a proposal to establish a DDA; and
WHEREAS this request has been reviewed by the TIF District Review
Policy Ad Hoc Committee as to the implications of the capture of County tax
dollars in the proposed development area; and
WHEREAS the County is in the process of purchasing the New Hudson
airport which will take several private hangers and a flight school off the
tax rolls for Lyon Township; and
WHEREAS the TIF District Review Policy Ad Hoc Committee recommends
participation in the proposed DDA.
NOW THEREFORE BE IT RESOLVED that the Oakland County Board of
Commissioners authorizes the County's participation in the Lyon Township
Downtown Development Authority, as identified in the attached map, subject to
a mutually agreeable contract being negotiated between the County and Lyon
Township.
BE IT FURTHER RESOLVED that the project is limited to streetscape
improvements, as detailed in the attached list.
BE IT FURTHER RESOLVED that the County's participation will sunset once
adequate funds are captured for the streetscape project.
Chairperson, on behalf of the Finance Committee, I move adoption of the
foregoing resolution.
FINANCE COMMITTEE
FINANCE COMMITTEE VOTE:
Motion carried unanimously on a roll call vote with Coleman, Millard and
Jensen absent.
UNIT DESCRIPTION UNIT QUANTITY PRICE TOTAL EXPLANATION ,
Grand River Avenue (approximately 10,560
linear feet of roadway)
Benches and Trash Receptacles each 15 $1,200.00 $18,000.00
Plantings - Perennials 1 gal 1000 $15.00 $15,000.00 Drifts of native perennials along R.O.W. -
Plantings - Shrubs 24-30" 350 $35.00 $12,250.00 Drifts of native shrubs
_ along R.O.W.
Signage (includes hardscape, Welcome sign, areas of
N.A. 1 N.A. $30,000.00 plantings, lighting) interest, parking etc.
Brick Crosswalks sq. ft. 600 $15.00 $9,000.00 To be installed at major
intersection
12-14' tall decorative
Decorative Street Lighting each 160 $4,000.00 $680,000.00 lamp post, approx. 140'
on center -
Miscellaneous N.A. N.A. N.A. $55,000.00 Grading, soil, drainage, and contingencies
GRAND RIVER AVENUE SUB-TOTAL $819,250.00
Milford Road (approximately 5,000 linear feet
of roadway)
Benches and Trash Receptacles each 7 $1,200.00 $8,400.00
_
2-2.5" Plantings - Trees 250 ' $400.00 $100,000.00 40' on center caliper
Drifts of native shrubs Plantings - Shrubs 24-30" 300 $35.00 $10,500.00 planted in R.O.W.
Drifts of native
Planting -Perennials 1 gal 3000 $15.00 $4,500.00 perennials within R.O.W.
Signage (includes hardscape,
N.A. 1 N.A. $20,000.00 Welcome sign plantings, lighting)
To be installed at major Brick Crosswalks sq. ft. 600 $15.00 $9,000.00 intersection
Approximately 140' on
center for 1000 L.F. both
Decorative Street Lighting each 16 $4,000.00 $64,000.00 sides of road, starting
from Grand River
Avenue
To be installed on one
Concrete Sidewalks - 5' wide sq. ft. 25,000 $6.00 $150,000.00 side of road only
McKenna Associates, Inc.
Preliminary Cost Estimate Prepared on 10/26/99
• •
I .
I.
Table 1 •
New Hudson StreetsciLpe Improvements
Lyon Township Downtown Development Authority
DESCRIPTION UNIT QUANTITY UNIT TOTAL EXPLANATION PRICE
270 ft. boardwalk, 30-ft.
Boardwalk and Pedestrian Bridge over bridge; cost estimate by
N.A. N.A. N.A. $110,000.00
New Hudson Drain Orchard, Hiltz &
_ McCliment, Inc.
Topsoil, grading, —
Miscellaneous - N.A. N.A. N.A. $40,000.00 drainage, and
_ _ contingencies
MILFORD ROAD SUB-TOTAL $516,400.00
Pontiac Trail (approximately 2,300 linear feet of
roadway) .
Benches and Trash Receptacles each 5 $1,200.00 $6,000.00
. .
2-2.5"
,
Plantings - Trees 125 $400.00 $50,000.00 40' on center caliper
Drifts of native "
Plantings - Shrubs 24-30" 150 $35.00 $5,250.00 perennials planted in
R.O.W.
Drifts of native shrubs Plantings - Perennials 1 gal 200 $15.00 $3,000.00 planted in R.O.W. _ . .
Signage (includes hardscape, Welcome sign, areas of
N.A. 1 N.A. $6,000.00
plantings, lighting) interest, parking, etc.
To be installed at major
Brick Crosswalks sq. ft. 600 $15.00 $9,000.00 intersection
Decorative Street Lighting each 35 $4,000.00 $140,000.00 Approx. 140' on center
Concrete Sidewalks - 5' wide sq. ft. 23,000 $6.00 $138,000.00 To beststallfedoodn both
' Topsoil, grading,
Miscellaneous N.A. N.A. N.A. $25,000.00 drainage, and _
contingencies
PONTIAC TRAIL SUB-TOTAL $382,250.00
Engineering, Landscape Architecture,
30% $515,370.00 Legal, Bonding, Administration
GRAND TOTAL $2,233,270.00 ,
w
•
UI
UI
Table 1 •
New Hudson Streetstape Improvements
Lyon Township Downtown Development Authority
McKenna Associates, Inc.
Preliminary Cost Estimate Prepared on 10/26/99
AMMenro =ME
Charter Township of Lyon, Oakland County, Michigan
n flon New Fire Station
and Water Tower
:Ida op". • Elsie P"
1111111 c-c-rwirg.
ET110 I nom _
ripi11112:1
Mobile Home Park Kensington
WI) I Wa rr!II
iiiiicii ea. iiiiiiiIiinuiiiii 'I
- #
E
;egAir
ill
1111111111111111111Q_
III
IIiEhIIhtIuhuaiahiiii1IIu
=nri
- —411111111111111111r=
•mi. Lai c-Tut:
M
1r I= ps, MIM O ME woo
/IV ... =Vail
d =7;7711111F3WA/Tir-a'..r il .......... i. r A e
25111111111111 :7211 1Ar . , romi rtiti " Lill h 1
;tr." P !Int
pa
r,--iiillsommurrig _ll_u_ millummilmir( ntr.. -
ESI Number of Parcels: 296 Total Acrea ge: 1114.62 ac.
Map 1 - Proposed Development Area and
Tax Increment Financing District Boundaries
= ;
2
March 20, 2000 itasernap Source: Orchard. KM. lAcarnent
Oda Source: McKenna Associates. Inc. 9/98
om,. 0.5 Mi. (i)
0.25 Mi.
FOREGOING RESO,LUTIC HEREBY APPRO
L. Brooks Patterson, County Executive
Resolution #00155 June 15, 2000
Moved by Douglas supported by Palmer the resolution be adopted.
Discussion followed.
AYES: Gregory, Jensen, Law, McCulloch, McPherson, Millard, Moffitt,
Obrecht, Palmer, Schmid, Sever, Suarez, Taub, Amos, Appel, Buckley,
Causey-Mitchell, Colasanti, Dingeldey, Douglas, Galloway, Garfield. (22)
NAYS: Melton, Coleman. (2)
A sufficient majority having voted therefor, the resolution was
adopted.
STATE OF MICHIGAN)
COUNTY OF OAKLAND)
I, G. William Caddell, Clerk of the County of Oakland, do hereby certify that the
foregoing resolution is a true and accurate copy of a resolution adopted by the
Oakland County Board of Commissioners on June 15, 2000 with the original record
thereof now remaining in my office.
In Testimony Whereof, I have hereunto set my hand and affixed the seal of the
County of Oakland at Pontiac, Michigan this 15th day,Eff June, 2000.
G.‘ William Caddell, County Clerk