HomeMy WebLinkAboutResolutions - 2019.05.23 - 31813MISCELLANEOUS RESOLUTION` #19189
BY: Commissioner Marcia Gershenson, District #13; Commissioner William Miller, District #14
IN RE: BOARD OF COMMISSIONERS—TRI-PARTY ROAD IMPROVEMENT PROGRAM FISCAL YEAR
2019 APPROPRIATION -- CHARTER TOWNSHIP OF WEST BLOOMFIELD — RIGHT-OF-WAY
ACQUISITION AT 14 MILE ROAD, NORTHWESTERN HIGHWAY, AND ORCHARD LAKE ROAD —
PROJECT NO. 48201
To the Oakland County Board of Commissioners:
Chairperson, Ladies and Gentlemen:
WHEREAS since the 1970s, the Oakland County Board of Commissioners has authorized the Tri -Party
Road Improvement Program to assist Oakland County's cities, villages and townships (CVTs) with the
construction, maintenance and repair of roads under the supervision, direction and control of the Road
Commission for Oakland County (RCOC); and
WHEREAS on December 6, 2018, the Board of Commissioners approved Miscellaneous Resolution
#18446 which designated $4,372,189 in fund balance for the Tri -Party Road Improvement Program for
projects managed by the RCOC; and
WHEREAS the Charter Township of West Bloomfield, along with the RCOC, has identified a project and
said project is ready to be undertaken immediately; and
WHEREAS the RCOC has appropriated its one-third (113) share of the funding for the project in the Charter
Township of West Bloomfield and said appropriation has been transferred to a project account; and
WHEREAS the Charter Township of West Bloomfield has demonstrated that it has authorized its one-third
(11 /3) share of the funding for the project and has executed a contract for payment with the RCOC; and
WHEREAS Oakland County's one-third (113) share of the Fiscal Year 2019 authorized amount of Tri -Party
Road Improvement funding for Project No. 48201 in the Charter Township of West Bloomfield is $122,168;
and
WHEREAS funding is available in the General Fund Assigned Fund Balance for Tri -Party 2019 and prior
funding (account #383510) for Project No. 48201 in the amount of $122,168.
NOW THEREFORE BE IT RESOLVED that the Oakland County Board of Commissioners hereby approves
the project submitted by the Charter Township of West Bloomfield and authorizes the release of Tri -Party
Road Improvement Program funds from the Oakland County Assigned Fund Balance.
BE IT FURTHER RESOLVED additional project costs, not greater than 15% from the original agreement,
which are consistent with the project as originally approved, will be paid when invoiced and appropriated in
the quarterly forecast resolution.
BE IT FURTHER RESOLVED that additional project costs exceeding 15% of the original agreement will
require a separate resolution.
BE IT FURTHER RESOLVED that the Oakland County Clerk is requested to forward copies of this
resolution to the Road Commission for Oakland County, Oakland County Fiscal Services and the Charter
Township of West Bloomfield,
BE IT FURTHER RESOLVED the FY 2019 budget will be amended as follows:
GENERAL FUND (#10100) FY 2019
Revenue
9010101-196030-665882 Planned Use of Balance $122,168
Total Revenue 22
Expenditures
9010101-153010-740135 Road Commission Tri -Party $122,168
Total Expenditures $122.10
Chairperson, I move the adoption of the foregoing Resolution,
Commissioner William Miller
District #14
Quality Life through Good Roads "We Care"
Inter -Departmental Memorandum
PROGRAMMING DIVISION
14A
DATE: April 29, 2019
To: Thomas G. Blust, P.E., Director of Engineering
FROM: Thomas G. Noechel, Programming Supervisor 7',& n
SUBJECT: PROJECT NO. 48201
ORCHARD LAKE ROAD, 14 MILE ROAD TO MAPLE ROAD AND
14 MILE ROADINORTHWESTERN HIGHWAYIORCHARD LAKE ROAD
LOCAL COST PARTICIPATION AGREEMENTITRI-PARTY PROGRAM
CHARTER TOWNSHIP OF WEST BLOOMFIELD
Attached for your review and submission to the Board for their approval is the local cost
participation agreement with the Charter Township of West Bloomfield for the right-of-way
acquisition for the roundabout construction at 14 Mile Road/Northwestern
Highway/Orchard Lake Road and the boulevard reconstruction of Orchard Lake Road
from 14 Mile Road to Maple Road. Construction on these projects has been completed.
The estimated total cost is $2,932,022 and will be partially funded with $2,199,016 from
the Michigan Department of Transportation due to a lawsuit settlement. The remaining
local match of $733,006 will be shared between the Charter Township of West Bloomfield
and the Board. The Charter Township of West Bloomfield has elected to use the Tri -
Party Program to fund their share of $366,503. Our total estimated share is $488,670
and is in the FY19 budget.
The projects are in the districts of County Commissioners Marcia Gershenson and William
Miller. The agreement is in our standard approved format, and I recommend Board
approval and authorize the Managing Director to execute the agreement on behalf of the
Board.
Ije
Attachments
Recommended for Board Approval
v � hlk,4LlI-Ulll
Thomas G. Blust, P.E.
Director of Engineering
r-,
Lm&0r.
COST PARTICIPATION AGREEMENT
RIGHT OF WAY ACQUISITION
Orchard Lake Road
14 Mile Road to Maple Road
and
14 Mile Road/Northwestern Highway/Orchard Lake Road Roundabout
Charter Township of West Bloomfield
Board Project No. 48201
This Agreement, made and entered into this 15th day of April... , 2019, by
and between the Board of County Road Commissioners of the County of Oakland, Michigan,
hereinafter referred to as the BOARD, and the Charter Township of West Bloomfield, hereinafter
referred to as the COMMUNITY, provides as follows:
WHEREAS, the BOARD and the COMMUNITY have programmed the right of way
acquisition for the boulevard reconstruction of Orchard Lake Road from 14 Mile Road to Maple
Road and the roundabout construction at 14 Mile Road/Northwestern Highway/Orchard Lake
Road, as described in Exhibit "A", attached hereto, and made a part hereof, which improvements
involve roads under the jurisdiction of the BOARD and within the COMMUNITY, which
improvements are hereinafter referred to as the RIGHT OF WAY; and
WHEREAS, the final total cost of the RIGHT OF WAY is $2,932,022; and
WHEREAS, the BOARD has received $2,199,096 from the Michigan Department of
Transportation due to a lawsuit settlement; and
WHEREAS, said RIGHT OF WAY involves certain designated and approved funding in
accordance with the Tri -Party Program in the amount of $366,503, which amount shall be paid
through equal contributions by the BOARD, the COMMUNITY and the Oakland County Board of
Commissioners, hereinafter referred to as the COUNTY; and
WHEREAS, the BOARD and the COMMUNITY have reached a mutual understanding
regarding the cost sharing for the LOCAL SHARE of the RIGHT OF WAY and wish to commit that
understanding to writing in this Agreement.
NOW, THEREFORE, in consideration of the mutual covenants set forth herein and in
conformity with applicable law, it is hereby agreed between the COMMUNITY and the BOARD
that;
1. The COMMUNITY approves of the RIGHT OF WAY, declares its public necessity,
and authorizes the BOARD to perform or cause to be performed, and complete the
RIGHT OF WAY along with all administration in reference thereto.
2. The RIGHT OF WAY is hereby defined as all costs necessary for the right-of-way
acquisition work including engineering, appraisals, acquisition, legal, financing, the
costs of technical guidance, monitoring, training and any other costs as may be
incurred by the BOARD as a result of this agreement. Any costs incurred by the
BOARD prior to this agreement date shall be allowable.
3. The total RIGHT OF WAY LOCAL SHARE of $733,006 shall be funded and invoiced
simultaneously as follows:
a. The BOARD shall contribute $366,503 or one-half of the LOCAL SHARE.
b. The COMMUNITY shall $366,503 or one half of the LOCAL SHARE and has
elected to use the Tri -Party Program to fund this share.
c. Any RIGHT OF WAY costs above the $733,006 LOCAL SHARE, shall be
funded 100% by the BOARD.
4. Upon execution of this Agreement, the BOARD shall submit an invoice to the
COMMUNITY for $122,168 (being 100% of the COMMUNITY'S Tri -Party
contribution).
Orchard Lake Road V4 Mile/NW Hwy/Orchard Lake 2
Charter Township of West Bloomfield
Project No.
4111209
5. After execution of this agreement and approval by the COUNTY, the BOARD shall
submit an invoice to the COUNTY in the amount of $122,168 (being 100% of the
COUNTY'S Tri -Party contribution).
a. The invoice shall be sent to:
Lynn Sonkiss, Manager of Fiscal Services
Executive Office Building
2100 Pontiac Lake Road, Building 41 West
Waterford, Ml 48328
6. Upon receipt of said invoice(s), the COMMUNITY and the COUNTY shall pay to the
BOARD the full amount thereof, within thirty (30) days of such receipt.
Orchard Lake Road 814 WeM Hwy/Orchard Lake 3
Charter Township of West Bloomfield
Project No.
4/1/2019
IN WITNESS WHEREOF, the parties hereto have executed this Agreement the day and
date first written above.
BOARD OF ROAD COMMISSIONERS OF THE
COUNTY OF OAKLAND
A Public Body Corporate
By
Steven Kaplan
CHARTER TOWNSHIP OF WEST BLOOMFIELD
By f:)Q- aen C�,Jv •
De—orah Binder
Its Clerk
Orchard Lake Road W4 WelNW HwylOrchard Lake
Charter Township of West Bloomfield
Project No.
411!2013
EXHIBIT A
TRI -PARTY PROGRAM
Orchard Lake Road, 14 Mile Road to Maple Road
and 14 Mile Road/Northwestern Highway/Orchard Lake Road Roundabout
Charter Township of West Bloomfield
Board Project No. 48201
The RIGHT OF WAY is hereby defined as all costs necessary for the right of way
acquisition work including engineering, appraisals, acquisition, legal, financing, the costs
of technical guidance, monitoring, training and any other costs necessary to complete the
right of way acquisition,
ESTIMATED PROJECT COST
Right of Way Acquisition (Final) $2,932,022
Less Lawsuit/MDOT
($2,199,016)
TOTAL RIGHT OF WAY ACQUISITION $733,006
COST PARTICIPATION BREAKDOWN
Orchard Lake Road &14 Mile/NW Hwy/Orchard Lake 5
Charter Township of West Bloomteld
Project No,
411/2019
COMMUNITY
COUNTY
BOARD
TOTAL
FY2018 Tri -Party Program
$101,088
$101,088
$101,087
$303,263
FY2019 Tri -Party Program
$21,080
$21,080
$21,080
$63,240
Contribution
$0
$0
$366,503
$3667503
TOTAL SHARES
$122,168
$122,168
$488,670
$733,006
Orchard Lake Road &14 Mile/NW Hwy/Orchard Lake 5
Charter Township of West Bloomteld
Project No,
411/2019
Resolution #19189
May 23, 2019
The Chairperson referred the resolution to the Economic Growth and Infrastructure Committee. There were
no objections.