HomeMy WebLinkAboutResolutions - 2021.06.17 - 34606MISCELLANEOUS RESOLUTION #21217 June 17, 2021
BY: Commissioners Tom Kuhn, District #11; Penny Luebs, District #16; Gary McGillivray, District 20
IN RE: BOARD OF COMMISSIONERS —TRI-PARTY ROAD IMPROVEMENT PROGRAM FISCAL YEAR
2021 APPROPRIATION — CITY OF TROY— CONCRETE SLAB REPLACEMENT — PROJECT NO. 66521
To the Oakland County Board of Commissioners:
Chairperson, Ladies and Gentlemen:
WHEREAS since the 1970s, the Oakland County Board of Commissioners has authorized the Tri-Party
Road Improvement Program to assist Oakland County's cities, villages and townships (CVTs) with the
construction, maintenance and repair of roads under the supervision, direction and control of the Road
Commission for Oakland County (RCOC); and
WHEREAS on December 7, 2020, the Board of Commissioners approved Miscellaneous Resolution
#20635 which designated $5,319,430 in fund balance for the Tri-Party Road Improvement Program for
projects managed by the RCOC; and
WHEREAS the City of Troy, along with the RCOC, has identified a project and said project is ready to be
undertaken immediately; and
WHEREAS the RCOC has appropriated its one-third (1/3) share of the funding for the project in the City of
Troy and said appropriation has been transferred to a project account; and
WHEREAS the City of Troy has demonstrated that it has authorized its one-third (1/3) share of the funding
for the project and has executed a contract for payment with the RCOC; and
WHEREAS Oakland County's one-third (1/3) share of the Fiscal Year 2021 authorized amount of Tri-Party
Road Improvement funding for Project No. 55521 in the City of Troy is $394,031; and
WHEREAS funding is available in the General Fund Assigned Fund Balance for Tri-Party 2021 and prior
funding (account #383510) for Project No. 55521 in the amount of $394,031.
NOW THEREFORE BE IT RESOLVED that the Oakland County Board of Commissioners hereby approves
the project submitted by the City of Troy and authorizes the release of Tri-Party Road Improvement Program
funds from the Oakland County Assigned Fund Balance.
BE IT FURTHER RESOLVED additional project costs, not greater than 15% from the original agreement,
which are consistent with the project as originally approved, will be paid when invoiced and appropriated in
the quarterly forecast resolution.
BE IT FURTHER RESOLVED that additional project costs exceeding 15% of the original agreement will
require a separate resolution.
BE IT FURTHER RESOLVED that the Oakland County Clerk is requested to forward copies of this
resolution to the Road Commission for Oakland County, Oakland County Fiscal Services and the City of
Troy.
BE IT FURTHER RESOLVED the FY 2021 budget will be amended as follows:
GENERAL FUND 410100) FY 2021
Revenue
9010101-196030-665882 Planned Use of Balance $394,031
Total Revenue $24 31
Expenditures
9010101-153010-740135 Road Commission Tri-Party $394,031
Total Expenditures
Chairperson, I move the adoption of the foregoing Resolution.
Commissioner Tom Kuhn Commiss4r Penny Luebs
Di trict #11 District #16
Commi sion Gary cGillivray
District #20
ECONOMIC DEVELOPMENT AND INFRASTRUCTURE COMMITTEE VOTE:
Motion carried on a roll call vote with Markham absent.
Qrmllip Li/i through Good Roods "We Care"
.ter:. •rrt..�.��l:�r�r
Inter —Departmental Memorandum
PROGRAMMING DIVISION
To: Samuel Fitzer, P.E., Director of Engineering
FROM: Thomas G. Noechel, Programming Supervisor
Q/1�
o5/2a/2r
DATE: May'I'l, 2021
SUBJECT: PROJECT NO. 55521, 2021 CONCRETE REPLACEMENT PROGRAM
VARIOUS COUNTY ROADS
LOCAL COST PARTICIPATION AGREEMENT/TRI-PARTY PROGRAM
CITY OF TROY
Attached for your review and submission to the Board for their approval is the local cost
participation agreement with the City of Troy for the concrete slab replacement work on
various county roads in the city. Construction on this project is expected to begin this
summer.
The estimated total cost is $7,125,000 and will be partially funded with Surface
Transportation Program Relief funds in the amount of $4,100,000, The remaining local
match of $3,025,000 will be shared between the City of Troy, Oakland County, and the
Board. Our total estimated share is $1,919,031 and is in the FY21 budget,
The project is in the districts Of County Commissioners Tom Kuhn, Penny Luebs, and
Gary McGillivray. The agreement is in our standard approved format, and I recommend
Board approval and authorize the Managing Director to execute the agreement on behalf
of the Board.
/je
Attachments
Recommended for Board Approval
Snnnicl HINT ,"""•
v„ a :,e � u n nni
Samuel Fitzer, PE
Director of Engineering
Lov�(u\r
16C
500 W,;.A 16g Ocave,
Tray, Nil 480H4
a: r
trnymt9ov
- -IA, 0111 c nN ----
CITY OF TROY
OAKLAND COUNTY, MICHIGAN
RESOLUTION
At a Regular meeting of the Troy City Council held on Monday, April 26, 2021, the following Resolution
was passed:
J-10 Cost Participation Agreement for 2021 Concrete Replacement Program with RCOC
Resolution #2021-04-060-J-10
Moved by Abrahim
Seconded by I-lodorelc
RESOLVED, That Troy City Council hereby APPROVES the Cost Participation Agreement between
the City of Troy and the Board of County Road Commissioners for Oakland County for the removal
and replacement of concrete pavement on various County roads at an estimated cost to the City of
Troy of $711,938, and the Mayor and City Clerk are AUTHORIZED TO EXECUTE the agreement, a
copy of which shall be ATTACHED to the original Minutes of this meeting,
FUnds for Troy's share of the work are included in the 2021 Capital Projects Fund, Project #
2021 C0038 (Account It 401.447.479.7989.500) and Project # 2021 C0029 (Account # 2021 C0029),
Yes: All-7
No: None
MOTION CARRIED
I, M, Aileen Dickson, duly appointed City Clerk of the City of Troy; do hereby certify that the foregoing
constitutes a true and complete copy of a resolution adopted by the Troy City Council at a Regular
Meeting duly called and held on Monday, the Twenty-sixth day of April, 2021,
M. Aileen Dickson, MMC, MIPMC II
City Clerk
COST PARTICIPATION AGREEMENT
CONSTRUCTION
2021.Concrete Replacement Program
Various County Roads
City of Troy
Board Project No. 55521
This Agreement, made and entered into this 20th day of May , 2021, by
and between the Board of County Road Commissioners of the County of Oakland, Michigan,
hereinafter referred to as the BOARD, and the City of Troy, hereinafter referred to as the
COMMUNITY, provides as follows:
WHEREAS, the BOARD and the COMMUNITY have programmed the concrete
replacement work on various county roads, as described in Exhibit "A", attached hereto, and made
a part hereof, which improvements involve roads under the jurisdiction of the BOARD and within
the COMMUNITY, which improvements are hereinafter referred to as the PROJECT; and
WHEREAS, the estimated total cost of the PROJECT is $7,125,000 (PART 1 = $2,000,000
Maintenance Department Concrete Program & PART 2 = $5,125,000 Engineering Department
Project); and
WHEREAS, said PROJECT (Part 1 and 2) involves certain designated and approved
Tri-Party Program funding in the amount of$1,182,093, which amount shall be paid through equal
contributions by the BOARD, the COMMUNITY and the Oakland County Board of
Commissioners, hereinafter referred to as the COUNTY; and
WHEREAS, the BOARD will enter into a contract with MDOT for partial funding of the
PROJECT (Part 2) with federal program dollars under the Surface Transportation Program
Emergency Relief funds in the amount of $4,100,000; and
WHEREAS, the BOARD, as the requesting party therein, will be the party financially
responsible to MDOT to bear all costs of the PROJECT (Part 2) in excess of federal funds,
hereinafter referred to as the LOCAL SHARE; and
WHEREAS, the BOARD and the COMMUNITY have reached a mutual understanding
regarding the cost sharing of the PROJECT and wish to commit that understanding to writing in
this Agreement.
NOW, THEREFORE, in consideration of the mutual covenants set forth herein and in
conformity with applicable law, it is hereby agreed between the COMMUNITY and the BOARD
that:
1. The COMMUNITY approves of the PROJECT, declares its public necessity, and
authorizes the BOARD to perform orcause to be performed, and complete the PROJECT
along with all administration in reference thereto.
2. The PROJECT shall include total payments to the contractor. Any costs incurred by the
BOARD prior to this agreement date shall be allowable.
3. The estimated total PROJECT cost for PART 1 is $2,000,000 and shall be invoiced and
funded proportionately and simultaneously as follows:
a. Tri-Party Program funding in the amount of $1,000,000.
b. The BOARD shall contribute the construction engineering.
c. The BOARD shall also contribute $1,000,000 toward the PROJECT.
d. Any PART 1 PROJECT costs above the $2,000,000 will be funded 100% by the
BOARD.
4. The estimated LOCAL SHARE for PART 2 is $1,025,000 and shall be invoiced and
funded proportionately and simultaneously as follows:
a. Tri-Party Program funding in the amount of $182,093.
b. The COMMUNITY shall contribute $317,907 toward the LOCAL SHARE.
c. The BOARD shall contribute the construction engineering.
2021 Concrole Replacement Program -2-
City of Troy
Project No. 55521
41012021
d. The BOARD shall contribute $525,000 toward the LOCAL SHARE.
e. Any PART 2 costs above $1,025,000 will be funded 100% by the BOARD.
5. Upon execution of this agreement, the BOARD shall submit an invoice to the
COMMUNITY in the amount of $711,938 (being 100% of the COMMUNITY'S Tri-Party
contribution for Part 1 & 2 and 100% of the COMMUNITY'S contribution for Part 2).
6. After execution of this agreement and approval by the COUNTY, the BOARD shall submit
an invoice to the COUNTY in the amount of $394,031 (being 100% of the COUNTY'S
Tri-Party contribution for Part 1 & 2).
a. The invoice shall be sent to:
Lynn Sonkiss, Manager of Fiscal Services
Executive Office Building
2100 Pontiac Lake Road, Building 41 West
Waterford, MI 48328
7. Upon receipt of said invoice(s), the COMMUNITY and the COUNTY shall pay to the
BOARD the full amount thereof, within thirty (30) days of such receipt.
2021 Concrete Replacement Program - 3 -
City of Troy
Project No. 55521
4/9/2021
IN WITNESS WHEREOF, the parties hereto have executed this Agreement the day and
date first written above.
BOARD OF ROAD COMMISSIONERS OF THE
COUNTY OF OAKLAND
A Public Body Corporate
LAP
Its Managing Director
CITY OF TROY
By
Its Mayor
Its City Clerk
2021 Concrete Replacement Program - 4 -
City o1 Troy
Pralm:t No. 55521
4/f112021
EXHIBIT A
TRI-PARTY PROGRAM
2021 Concrete Replacement Program
Various County Roads
City of Troy
Board Project No. 55521
Concrete slab replacement on various county roads in the City of Troy.
ESTIMATED PROJECT COST
Part 1 - Maintenance Department
$2,000,000
Part 2 - Engineering Department
$5,125,000
TOTAL FOR PART 1 & 2
$7,125,000
Less Federal Funds for Part 2
$4,100,000
Total Estimated Project Cost
$3,025,000
COST PARTICIPATION BREAKDOWN
COMMUNITY
COUNTY
BOARD
TOTAL
(PART 1:
$p
IFY2020 Tri-Party Program
$195,213
$195,213
$195,214
$585,640
IFY2021 Tri-Party Program
$138,120
$138,120
$138,120
$414,360
(Contribution
$01
$0
$1,000,000
$1,000,000
IPART 2:
I
IFY2021 Tri-Party Program
$60,698 I
$60,698
$60,697
$182,093
(Contribution
$317,907
$0
$525,000
$842,907
ITOTAL SHARES
$711,938
$394,031
$1,919,031
$3,025,000
2021 Concrete Replacement Program - 5 -
City of Troy
Project No. 55521
4r012021
Resolution #21217 June 17, 2021
Moved by Gingell seconded by Hoffman the resolutions on the amended Consent Agenda be adopted.
AYES: Charles, Gershenson, Gingell, Hoffman, Jackson, Joliet, Kochenderfer, Kowall, Kuhn,
Long, Luebs, Markham, McGillivray, Miller, Moss, Nelson, Spisz, Weipert, Woodward, Cavell. (20)
NAYS: None. (0)
A sufficient majority having voted in favor, the resolutions on the amended Consent Agenda were adopted.
a
I HEREBY APPROVE THIS RESOLUTION
CHIEF DEPUTY COUNTY EXECUTIVE
ACTING PURSUANT TO MCL 45.559A (7)
STATE OF MICHIGAN)
COUNTY OF OAKLAND)
I, Lisa Brown, Clerk of the County of Oakland, do hereby certify that the foregoing resolution is a true and
accurate copy of a resolution adopted by the Oakland County Board of Commissioners on June 17, 2021,
with the original record thereof now remaining in my office.
In Testimony Whereof, I have hereunto set my hand and affixed the seal of the Circuit Court at Pontiac,
Michigan this 171h day of June, 2021.
Lisa Brown, Oakland County