MISCELLANEOUS RESOLUTION #21-468
Sponsored By: Philip Weipert
IN RE: Board of Commissioners - Resolution Fiscal Year 2022 Appropriation with the City of South
Lyon for Tri-Party Road Improvement Program - Project No. 56331
Chairperson and Members of the Board:
WHEREAS since the 1970s, the Oakland County Board of Commissioners has authorized the Tri-Party Road
Improvement Program to assist Oakland County .s cities. villages and townships (CVTs) with the construction,
maintenance and repair of roads under the supervision, direction and control of the Road Commission for
Oakland County (RCOC); and
WHEREAS on September 29, 2021, the Oakland County Board of Commissioners approved Miscellaneous
Resolution #21375 which appropriated $2,000,000 for the FY 2022 Tri-Party Road Improvement Program
allocation for projects managed by the RCOC; and
WHEREAS the City of South Lyon, along with the RCOC, has identified a project and said project is ready to
be undertaken immediately; and
WHEREAS the project meets the terms and conditions of the Tri-Party Road Improvement Program and the
local cost participation agreement.
NOW THEREFORE BE IT RESOLVED that the Oakland County Board of Commissioners hereby approves
the project submitted by the City of South Lyon and authorizes the transfer of Tri-Party Road Improvement
Program funds in the amount of $9,361 from Non -Departmental Transfers appropriation (9090101).
BE IT FURTHER RESOLVED additional project costs. not greater than 15% from the original agreement.
-,which are consistent with the project as originally approved, will be paid when invoiced and appropriated in the
quarterly forecast resolution.
BE IT FURTHER RESOLVED that additional project costs exceeding 154 0 of the original agreeurent will
require a separate resolution.
BE IT FURTHER RESOLVED that the Oakland County Clerk is requested to forward copies of this
resolution to the Road Commission for Oakland County. Oakland County Fiscal Services, and the City of South
Lyon.
BE IT FURTHER RESOLVED the FY 2022 budget will be amended as follows:
GENERAL FUND (#10100) FY 2022
Expenditures
9010101-153010-740135 Road Commission Tri-Party $9,361
9090101-196030-740135 Road Commission Tri-Party ($9,361)
Total Expenditures $ 0
Chairperson, the following Conuuissioners are sponsoring the foregoing Resolution: Philip Weipert.
(21d Date: December 09, 2021
David Woodward, Commissioner
Date: December 15, 2021
Hilarie Chambers, Deputy County Executive 11
flu ( &V..'
Date: December 15, 2021
Lisa Brown, County Clerk / Register of Deeds
COMMITTEE TRACKING
2021-12-0I Economic Development &u Infrastructure - recommend to Board
2021-12-09 Full Board
VOTE TRACKING
Motioned by Commissioner William Miller III seconded by Commissioner Robert Hoffman to adopt the
attached Resolution: Fiscal Year 2022 Appropriation xvith the City of South Lyon for Tri-Party Road
Improvement Program —Project No. 56331.
Yes: David Woodward, Michael Gingell, Michael Spisz. Karen Joliat, Kristen Nelson, Eileen Kowall,
Christine Long, Philip Weipert, Gwen Markham, Angela Powell, Thomas Kuhn, Chuck Moss, Marcia
Gershenson, William Miller III, Yolanda Smith Charles. Charles Cavell. Penny Luebs, Janet Jackson, Gary
McGillivray, Robert Hoffinan, Adam Kochenderfer (21)
No: None (0)
Abstain: None (0)
Absent: (0)
The Motion Passed.
ATTACHMENTS
L. 56331 Tri-Parry - South Lyon
STATE OF MICHIGAN)
COUNTY OF OAKLAND)
I, Lisa Brown, Clerk of the County of Oakland, do hereby certify that the foregoing resolution is a true and
accurate copy of a resolution adopted by the Oakland County Board of Commissioners on December 9. 2021,
with the original record thereof now remaining in my office.
In Testimony Whereof, I have hereunto set my hand and affixed the seal of the Circuit Court at Pontiac.
Michigan on Thursday. December 9, 2021,
Liso Brown, Oakland County Clerk/Register ofDeeds
DATE:
To:
FROM:
Quality Life through Good Roads "We Care"
Inter —Departmental Memorandum
Programming Division
October 21, 2021
Samuel Fitzer, P.E., Director of Engineering
Thomas G. Noechel, Programming Supervisor-TGN
10M
Roc
��A�°a veGl
iii�4tz�Gl �,,,
Quarles / Fowkes
SUBJECT: PROJECT NO. 56331, PONTIAC TRAIL
YERKES DRAIN TO NORTH OF 10 MILE ROAD
LOCAL COST PARTICIPATION AGREEMENT/TRI-PARTY PROGRAM
CITY OF SOUTH LYON
Attached for your review and submission to the Board for their approval is the local cost
participation agreement with the City of South Lyon for a drainage study on Pontiac Trail from
Yerkes Drain to North of 10 Mile Road. The drainage study is expected to begin this fall.
The estimated total cost is $56,168. The City of South Lyon has elected to use the Tri-Party
Program to fund their share of $28,084 along with a $28,084 contribution from the Board. Our
share is estimated to be $37,446 which is in the FY22 budget.
The project is in the district of County Commissioner Phil Weipert. The agreement is in, our
standard approved format, and I recommend Board approval and authorize the Managing
Director to execute the agreement on behalf of the Board.
TGN/II
Attachments
Samuel
e�msk.fiwrseeoo org�c115
Department Review / Approval
J
Garyour°=e.rvoi°errwni
r,=amc
a=e�oo,
Piotrowicz
J
oa,e z z
Moo Review / Concur
I
COST PARTICIPATION AGREEMENT
DRAINAGE STUDY
Pontiac Trail
Yerkes Drain to North of 10 Mile Road
City of South Lyon
Board Project No. 56331
This Agreement, made and entered into this 4th day of November , 2021, by
and between the Board of County Road Commissioners of the County of Oakland, Michigan,
hereinafter referred to as the BOARD, and the City of South Lyon, hereinafter referred to as the
COMMUNITY, provides as follows:
WHEREAS, the BOARD and the COMMUNITY have programmed the Drainage Study on
Pontiac Trail from Yerkes Drain to north of 10 Mile Road, as described in Exhibit "A", attached
hereto, and made a part hereof, which improvements involve roads under the jurisdiction of the
BOARD and within the COMMUNITY, which improvements are hereinafter referred to as the
DRAINAGE STUDY; and
WHEREAS, the estimated total cost of the DRAINAGE STUDY is $56,168; and
WHEREAS, said DRAINAGE STUDY involves certain designated and approved Tri-Party
Program funding in the amount of $28,084, which amount shall be paid through equal
contributions by the BOARD, the COMMUNITY, and the Oakland County Board of
Commissioners, hereinafter referred to as the COUNTY; and
WHEREAS, the BOARD and the COMMUNITY have reached a mutual understanding
regarding the cost sharing of the DRAINAGE STUDY and wish to commit that understanding to
writing in this Agreement.
NOW, THEREFORE, in consideration of the mutual covenants set forth herein and in
conformity with applicable law, it is hereby agreed between the COMMUNITY and the BOARD
that:
1. The COMMUNITY approves of the DRAINAGE STUDY, declares its public necessity,
and authorizes the BOARD to perform or cause to be performed, and complete the
DRAINAGE STUDY along with all administration in reference thereto.
2. The DRAINAGE STUDY shall include total payments to the contractor. Any costs
incurred by the BOARD prior to this agreement date shall be allowable.
3. The estimated total DRAINAGE STUDY cost of $56,168 shall be shared equally by the
BOARD and the COMMUNITY. Each 50% share is estimated to be $28,084,
respectively. The COMMUNITY shall use the Tri-Party Program to fund their $28,084
share. The COMMUNITY also agrees that any cost overages shall be shared equally by
the BOARD and the COMMUNITY.
4. Upon execution of this agreement, the BOARD shall submit an invoice to the
COMMUNITY in the amount of $9,361 (being 100% of the COMMUNITY'S Tri-Party
contribution).
5. After execution of this agreement and approval by the COUNTY, the BOARD shall submit
an invoice to the COUNTY in the amount of $9,361 (being 100% of the COUNTY'S
Tri-Party contribution).
a. The invoice shall be sent to:
Lynn Sonkiss, Manager of Fiscal Services
Executive Office Building
2100 Pontiac Lake Road, Building 41 West
Waterford, MI 48328
6. Upon receipt of said invoice(s), the COMMUNITY and the COUNTY shall pay to the
BOARD the full amount thereof, within thirty (30) days of such receipt.
Pontiac Trail - 2 -
City of South Lyon
Project No. 56331
9/2312021
IN WITNESS WHEREOF, the parties hereto have executed this Agreement the day and
date first written above.
BOARD OF ROAD COMMISSIONERS OF THE
COUNTY OF OAKLAND
A Public Body Corporate
j j/ Dennis G. Kolar
By L..... Nov 4 2021 2:38 PM
Its Managing Director
CITY OF SOUTH LYON
By J A
Its
Pontiac Trail - 3 -
City of South Lyon
Project No. 66331
9123/2021
EXHIBIT A
TRI-PARTY PROGRAM
Pontiac Trail
Yerkes Drain to North of 10 Mile Road
City of South Lyon
Board Project No. 56331
Drainage study to be performed on Pontiac Trail from Yerkes Drain to north of 10 Mile Road.
ESTIMATED DRAINAGE STUDY COST
Contractor Payments $56,168
COST PARTICIPATION BREAKDOWN
COMMUNITY
COUNTY
BOARD
TOTAL
IFY2019 Tri-Party Program
$5,898
$5,899
$5,899
$17,696
IFY2020 Tri-Party Program
$3,463
$3,462
$3,463
$10,388
(Contribution
$0
$0
$28,084
$28,084
(TOTAL SHARES
$9,361
$9,361
$37,446
$56,168 I