BOARD OF COMMISSIONERS
February 24, 2022
MISCELLANEOUS RESOLUTION #22-039
Sponsored By: Kristen Nelson
IN RE: Board of Commissioners - Road Improvement Fiscal Year 2022 Appropriation with the City of
Keego Harbor for Tri-Party Road Improvement Program — Project No. 56591
Chairperson and Members of the Board:
WHEREAS since the 1970s, the Oakland County Board of Commissioners has authorized the Tri-Party Road
Improvement Program to assist Oakland County's cities, villages and townships (CVTs) with the construction,
maintenance and repair of roads under the supervision, direction and control of the Road Commission for
Oakland County (RCOC); and
WHEREAS on September 29, 2021, the Oakland County Board of Commissioners approved Miscellaneous
Resolution #21378 which appropriated $2,000,000 for the FY 2022 Tri-Party Road Improvement Program
allocation for projects managed by the RCOC; and
WHEREAS the City of Keego Harbor, along with the RCOC, has identified a project and said project is ready
to be undertaken immediately; and
WHEREAS the project meets the terms and conditions of the Tri-Party Road Improvement Program and the
local cost participation agreement.
NOW THEREFORE BE IT RESOLVED that the Oakland County Board of Commissioners hereby approves
the project submitted by the City of Keego Harbor and authorizes the transfer of Tri-Party Road Improvement
Program funds in the amount of $100,000 from Non -Departmental Transfers appropriation (9090101).
BE IT FURTHER RESOLVED additional project costs, not greater than 15% from the original agreement,
which are consistent with the project as originally approved, will be paid when invoiced and appropriated in the,
quarterly forecast resolution.
BE IT FURTHER RESOLVED that additional project costs exceeding 15% of the original agreement will
require a separate resolution.
BE IT FURTHER RESOLVED that the Oakland County Clerk is requested to forward copies of this
resolution to the Road Commission for Oakland County, Oakland County Fiscal Services, and the City of
Keego Harbor.
BE IT FURTHER RESOLVED that the FY 2022 budget shall be amended as described in the attached
Schedule A — Budget Amendment.
Chairperson, the following Commissioners are sponsoring the foregoing Resolution: Kristen Nelson.
(tzjdl�u Date: February 25, 2022
David Woodward, Commissioner
��, o �/�/y)nw�
^�`^°' ®" Date: February 28, 2022
Hilarie Chambers, Deputy County Executive II
FJ
P Date: March 01, 2022
Lisa Brown, County Clerk / Register of Deeds
COMMffTEE TRACKING
2023-02-09 Economic Development & Infrastructure - Recommend to Board
202 2-02-24 Full Board
VOTE TRACKING
Motioned by Commissioner Penny Luebs seconded by Commissioner Karen Joliat to adopt the attached Road
Improvement : Fiscal Year 2022 Appropriation with the City of Keego Harbor for Tn-Party Road Improvement
Program —Project No. 56591.
Yes: David Woodward, Michael Gingell, Michael Spisz, Karen Joliat, Kristen Nelson, Eileen Kovvall,
Christine Long, Philip Weipert, Gwen Markham, Angela Powell, Thomas Kuhn, Charles Moss, Marcia
Gershenson, William Miller III, Yolanda Smith Charles, Charles Cavell, Penny Luebs, Janet Jackson, Gaiy
McGillivray, Robert Hoffman (20)
No: None (0)
Abstain: None (0)
Absent: (0)
The Motion Passed.
ATTACHMENTS
1. Schedule A - Budget Amendment - Project No. 56591
2. 56591 Tri-Party - Keego Harbor Agreement
STATE OF MICHIGAN)
COUNTY OF OAKLAND)
I, Lisa Brown, Clerk of the County of Oakland, do hereby certify that the foregoing resolution is a true and
accurate copy of a resolution adopted by the Oakland County Board of Commissioners on February 24, 2022.,
with the original record thereof now remaining in my office.
In Testimony Whereof, I have hereunto set my hand and affixed the seal of the Circuit Court at Pontiac,
Michigan on Thursday, February 24, 2022.
Lisa Brown Oakland Counh, Clerk/ Register of Deeds
-- ovement Pro9Y°m'
Mot.aW, 56591
,.egoR rpor for TnAattN Road �� B oard of .FisealYeat 2922 PPP nwO�on�WUSntY9+t�n apnfiCynd{Y�u
sieRak:ryaetwt nocnus�nt
„p�Atl �TTrr7
Proro ectgocom"S
SW
a m oida
"mtsston
Wres Y`
ram# perpunt# Umt
rig Otvtst°n# P gn013S
FUM1 15?Ai� 7A0135
ptvisioM1 Name �10101 M193��
tOtO� yggpWt
Fund Nana went ipiCM1
WE Noce hem
e�Fand Nnn-OeP
E � o�Fund
E
12A
DATE:
To:
FROM:
SUBJECT:
Quality Life through Good Roads "We Care"
.4
.� .,,zt
IF FUF WA it
Inter -Departmental Memorandum
Programming Division
January 7, 2022
Samuel Fitzer, P.E., Director of Engineering
Thomas G. Noechel, Programming Supervisor76N
RC0C
74pprU ve
01/20/2022
Quarles / Fowkes
PROJECT NO. 56591, CASS LAKE ROAD
ORCHARD LAKE ROAD TO OTTER AVENUE
LOCAL COST PARTICIPATION AGREEMENT/TRI-PARTY PROGRAM
CITY OF KEEGO HARBOR
Attached for your review and submission to the Board for their approval is the local cost
participation agreement with the City of Keego Harbor for the concrete slab replacement
work on Cass Lake Road from Orchard Lake Road to Otter Avenue. Construction on this
project is expected to begin this fiscal year.
The City of Keego Harbor has elected to use the Tri-Party Program of $300,000 to partially
fund the estimated total project cost of $375,000. Our share is estimated to be $100,000
along with a contribution of $75,000 and is in the FY22 budget.
The project is in the district of County Commissioner Kristen. The agreement is in our
standard approved format, and I recommend Board approval and authorize the Managing
Director to execute the agreement on behalf of the Board.
TGN/II
Attachments
plgllaIM signed by 1—d Flle,
pN cn=SamuelFlaec mEn9lneeeln9
Samuel Fitzer
rcna�l-Sf ��ia^eo,g. e_115
wee mzzm a oawvasm
Department Review / Approval
Gary p�gilaly WgneE by Gary P,tl l¢
pM Gay Plo4ovncz, o-Fcoc,
'_moo,
Piotrowicz pale ROP3011 0B'[1�05Op'S
MDO Review / Concur
CONSTRUCTION
Cass Lake Road
Orchard Lake Road to Otter Avenue
City of Keego Harbor
Board Project No. 56591
This Agreement, made and entered into this 20th day of January , 2022, by
and between the Board of County Road Commissioners of the County of Oakland, Michigan,
hereinafter referred to as the BOARD, and the City of Keego Harbor, hereinafter referred to as
the COMMUNITY, provides as follows:
WHEREAS, the BOARD and the COMMUNITY have programmed the concrete slab
replacement work on Cass Lake Road from Orchard Lake Road to Otter Avenue, as described in
Exhibit "A", attached hereto, and made a part hereof, which improvements involve roads under
the jurisdiction of the BOARD and within the COMMUNITY, which improvements are hereinafter
referred to as the PROJECT; and
WHEREAS, the estimated total cost of the PROJECT is $375,000; and
WHEREAS, said PROJECT Involves certain designated and approved Tri-Party Program
funding in the amount of $300,000, which amount shall be paid through equal contributions by the
BOARD, the COMMUNITY, and the Oakland County Board of Commissioners, hereinafter
referred to as the COUNTY; and
WHEREAS, the BOARD and the COMMUNITY have reached a mutual understanding
regarding the cost sharing of the PROJECT and wish to commit that understanding to writing in
this Agreement.
NOW, THEREFORE, in consideration of the mutual covenants set forth herein and in
conformity with applicable law, it is hereby agreed between the COMMUNITY and the BOARD
that:
Cass Lake Road - 1 -
City of Keego Harbor
Project No. 56591
f 0/20/2021 .. .. ...
1. The COMMUNITY approves of the PROJECT, declares its public necessity, and
authorizes the BOARD to perform or cause to be performed, and complete the PROJECT
along with all administration in reference thereto.
2. The PROJECT shall include total payments to the contractor. Any costs incurred by the
BOARD prior to this agreement date shall be allowable.
3. The estimated total PROJECT cost of $375,000 shall be invoiced simultaneously and
proportionately as follows:
a. Tri-Party Program funding in the amount of $300,000.
b. The COMMUNITY shall contribute $300,000 toward the LOCAL SHARE and the
BOARD shall contribute $75,000 toward the LOCAL SHARE, simultaneously.
c. Any PROJECT costs above $375,000 will be funded 100% by the BOARD.
4. Upon execution of this agreement, the BOARD shall submit an invoice to the
COMMUNITY in the amount of $100,000 (being 100% of the COMMUNITY'S Tri-Party
contribution).
5. After execution of this agreement and approval by the COUNTY, the BOARD shall submit
an invoice to the COUNTY in the amount of $100,000 (being 100% of the COUNTY'S
Tri-Party contribution).
a. The invoice shall be sent to:
Lynn Sonkiss, Manager of Fiscal Services
Executive Office Building
2100 Pontiac Lake Road, Building 41 West
Waterford, MI 48328
6. Upon receipt of said invoice(s), the COMMUNITY and the COUNTY shall pay to the
BOARD the full amount thereof, within thirty (30) days of such receipt.
Cass Lake Road - 2 -
City of Keego Harbor
Project No. 56591
10120/2021
IN WITNESS WHEREOF, the parties hereto have executed this Agreement the day and
date first written above.
BOARD OF ROAD COMMISSIONERS OF THE
COUNTY OF OAKLAND
A Public Body Corporate
"1 �L/lj Dennis G. Kolar
By
d"U� L Jan 20 2022 1:27 PM
Its Managing Director
CITY OF KEEGO HARBOR
B_�
Its i
Cass Lake Road "
City of Keego Harbor
Prole -et W 56591
10/20/2021
TRI-PARTY PROGRAM
Cass Lake Road
Orchard Lake Road to Otter Avenue
City of Keego Harbor
Board Project No. 56591
Concrete slab replacement on Cass Lake Road from Orchard Lake Road to Otter
Avenue.
ESTIMATED PROJECT COST
Contractor Payments $375,000
Total Estimated Project Cost $375,000
IFY06 Tri-Party Program
FY07 Tri-Parry Program
FY08 Tri-Party Program
FY09 Tri-Party Program
FYI Tri-Party Program
FYI Tri-Party Program
FY12 Tri-Party Program
FY13 Tri-Party Program
FY14 Tri-Party Program
FYI Tri-Party Program
FY16 Tri-Party Program
FY17 Tri-Party Program
FY18 Tri-Party Program
FY19 Tri-Party Program
FY20 Tri-Party Program
Contribution
TOTAL SHARES
Cass Lake Road
City of Keego Harbor
Project No. 56591
10/20/2021
COST PARTICIPATION BREAKDOWN
COMMUNITY
COUNTY
BOARD
TOTAL
$7,856
$7,856
$7,856
$23,567
$8,071
$8,071
$8,071
$24,214
$8,049
$8,049
$8,049
$24,146
$8,049
$8,049
$8,049
$24,146
$3,715
$3,715
$3,715
$11,146
$3,576
$3,576
$3,576
$10,727
$3,988
$3,988
$3,988
$11,964
$4,661
$4,661
$4,661
$13,983
$4,829
$4,829
$4,829
$14,487
$4,725
$4,725
$4,725
$14,176
$9,195
$9,195
$9,195
$27,586
$9,236
$9,236
$9,236
$27,708
$8,701
$8,701
$8,701
$26,102
$8,164
$8,164
$8,164
$24,491
$7,186
$7,186
$7,186
$21,557
$0
$0
$75,000
$75,000
$100'000
$100,000
$175,000
$375,000