AGENDA ITEM: Resolution to Authorize Jail Elevators 1 & 3 Hydraulic Jack Replacements Project
22-365
COMMITTEE MEETING: Board of Commissioners
DATE: Thursday, November 17, 2022 6:00 PM - Click to View Agenda
ITEM SUMMARY SHEET
DEPARTMENT SPONSORED BY
Facilities Maintenance and Operations William Miller III
INTRODUCTION AND BACKGROUND
POLICY ANALYSIS
The request is for authorization of the Jail Elevators 1 & 3 Hydraulic Jack Replacements
project. The existing Jail passenger elevators 1 & 3 are over 30 years old and have been taken out
of service repeatedly due to unsafe operation related to hydraulic jack oil leakage. The emergency
repair will include well drilling of the old hydraulic jacks, installing new hydraulic cylinder liners,
installing new jack shafts, emergency battery back-up, and related components.
Purchasing Division solicited proposals for the hydraulic jack replacements and the lowest
responsible bidder was Schindler Elevator Corporation of Livonia. The total project cost is
$404,900, including $364,574 for materials and installation, $5,000 for elevator consulting services,
as well as $35,326 (10%) for contingencies.
The FY 2023 – FY 2032 Capital Improvement Program (CIP) includes funding in the amount of
$200,000 for elevator maintenance and the remaining funds will be derived from the savings of
previously approved elevator maintenance and life safety enhancement projects that were
completed under budget in FY 2022.
On approval of the Board, the funds will be transferred in the amount of $404,909 from the Capital
Improvement Program/Building Fund (#40100) to the Project Work Order Fund (#40400) to
establish the Jail Elevators 1 & 3 Hydraulic Jack Replacements Project (PROJ-17163). The budget
is amended as detailed in Schedule A.
BUDGET AMENDMENT REQUIRED: No
Committee members can contact Michael Andrews, Policy and Fiscal Analysis Supervisor at
248.858.5115 (office) or andrewsmb@oakgov.com, or the department contact persons listed for
additional information.
CONTACT
Joseph Murphy
ITEM REVIEW TRACKING
William Miller III, Created/Initiated - 11/17/2022
David Woodward, Board of Commissioners Approved - 11/17/2022
Hilarie Chambers, Executive's Office Approved - 11/21/2022
Lisa Brown, Clerk/Register of Deeds Final Approval - 11/21/2022
AGENDA DEADLINE: 11/17/2022 6:00 PM
COMMITTEE TRACKING
2022-11-02 Economic Development & Infrastructure - Recommend to Board
2022-11-17 Full Board - Adopted
ATTACHMENTS
1. Schedule A Elevator Project
2. MR Project Estimate Jail Jacks 1 and 3 Replacement
November 17, 2022
RESOLUTION #2022-2161 _ 22-365
Sponsored By: William Miller III
Facilities Maintenance and Operations - Resolution to Authorize Jail Elevators 1 & 3 Hydraulic
Jack Replacements Project
Chairperson and Members of the Board:
WHEREAS the safety of employees and the public at county-owned buildings involves many building
systems and features, including safe, problem-free elevator/lift units; and
WHEREAS the existing Jail passenger elevators 1 & 3 are over 30 years old and have been taken
out of service repeatedly due to unsafe operation related to hydraulic jack oil leakage; and
WHEREAS the emergency repair will include well drilling of the old hydraulic jacks, installing new
hydraulic cylinder liners, installing new jack shafts, emergency battery back-up, and related
components; and
WHEREAS in accordance with Purchasing Division policies and procedures, Facilities Maintenance
and Operations (FM&O) and the Purchasing Division solicited proposals for the hydraulic jack
replacements and the lowest responsible bidder was Schindler Elevator Corporation of Livonia; and
WHEREAS the total project cost is $404,900, including $364,574 for materials and installation,
$5,000 for elevator consulting services, as well as $35,326 for contingencies; and
WHEREAS the FY 2023 – FY 2032 Capital Improvement Program (CIP) includes funding in the
amount of $200,000 for elevator maintenance; and
WHEREAS the remainder of the funds will be derived from savings of previously approved elevator
maintenance and life safety enhancement projects as these projects came under budget in FY 2022,
resulting in the availability of funds for the replacement of hydraulic jacks at the Jail; and
WHEREAS funding in the amount of $404,900 is available for transfer from the FY2023 Capital
Improvement Program/Building Fund (#40100) to the Project Work Order Fund (#40400) for the Jail
Elevators 1 & 3 Hydraulic Jack Replacements Project.
NOW THEREFORE BE IT RESOLVED that the Oakland County Board of Commissioners authorizes
the Jail Elevators 1 & 3 Hydraulic Jack Replacements project in the amount of $404,900.
BE IT FURTHER RESOLVED that the Board of Commissioners authorizes the transfer of funding for
the Jail Elevators 1 & 3 Hydraulic Jack Replacements Project (PROJ-17163) in the amount of
$404,909 from the Capital Improvement Program/Building Fund (#40100) to the Project Work Order
Fund (#40400) as detailed in the attached Schedule A.
BE IT FURTHER RESOLVED the remainder of the funds will be derived from the savings of the
previously approved elevator maintenance and life safety enhancement projects in FY 2022, as the
projects came under budget, resulting in the availability of funds within the FY 2023 CIP.
Chairperson, the following Commissioners are sponsoring the foregoing Resolution: William Miller
III.
Date: November 17, 2022
David Woodward, Commissioner
Date: November 21, 2022
Hilarie Chambers, Deputy County Executive II
Date: November 21, 2022
Lisa Brown, County Clerk / Register of Deeds
COMMITTEE TRACKING
2022-11-02 Economic Development & Infrastructure - Recommend to Board
2022-11-17 Full Board - Adopted
VOTE TRACKING
Motioned by Commissioner Kristen Nelson seconded by Commissioner Michael Spisz to adopt the
attached Resolution: to Authorize Jail Elevators 1 & 3 Hydraulic Jack Replacements Project.
Yes: David Woodward, Michael Spisz, Karen Joliat, Kristen Nelson, Christine Long, Philip Weipert,
Gwen Markham, Thomas Kuhn, Chuck Moss, Marcia Gershenson, William Miller III, Charles
Cavell, Penny Luebs, Janet Jackson, Gary McGillivray, Robert Hoffman, Adam Kochenderfer (17)
No: None (0)
Abstain: None (0)
Absent: (0)
Passed
ATTACHMENTS
1. Schedule A Elevator Project
2. MR Project Estimate Jail Jacks 1 and 3 Replacement
STATE OF MICHIGAN)
COUNTY OF OAKLAND)
I, Lisa Brown, Clerk of the County of Oakland, do hereby certify that the foregoing resolution is a true
and accurate copy of a resolution adopted by the Oakland County Board of Commissioners on
November 17, 2022, with the original record thereof now remaining in my office.
In Testimony Whereof, I have hereunto set my hand and affixed the seal of the Circuit Court at
Pontiac, Michigan on Thursday, November 17, 2022.
Lisa Brown, Oakland County Clerk / Register of Deeds
Oakland County, Michigan
FACILITIES MANAGEMENT/FACILITIES MAINTENANCE AND OPERATIONS - Jail Elevators 1 & 3 Hydraulic Jack Replacement Project
Schedule "A" DETAIL
R/E Fund Name Division Name
Fund #
(FND)Cost Center (CCN) #
Account #
(RC/SC)
Program #
(PRG)Grant ID (GRN) #
Project ID #
(PROJ)
Region
(REG)
Budget
Fund
Affiliate
(BFA)
Ledger
Account
Summary Account Title
FY 2022
Amendment
FY 2023
Amendment
FY 2024
Amendment
E Building Improvement Facilities Engineering Admin FND40100 CCN1040801 SC788001 PRG148020 40400 Transfer Out $-$(404,900.00)$-
Total Expenditures $-$(404,900.00)$-
R Project Work Order Facilities Engineering Admin FND40400 CCN1040801 RC695500 PRG148020 PROJ-17163 40100 Transfer In $-$404,900.00 $-
Total Revenues $-$404,900.00 $-
! "
#
$ $%
&'#
()$
*
'+ ,
! "#$%&' !()* +,-.-/
-.!+./
$0,
'+ 1 2
01&+.,/
-+!/
$01 2
3
,4
#---1 213 "1 4" +./
-+!/
$0,4
140
56
$735**8*90
-!+./
-..!/
05#5