AGENDA ITEM: Main Jail Complex Fencing and Gate Project
DEPARTMENT: Facilities Planning & Engineering
MEETING: Board of Commissioners
DATE: Thursday, July 18, 2024 6:00 PM - Click to View Agenda
ITEM SUMMARY SHEET
COMMITTEE REPORT TO BOARD
Resolution #2024-4255
Motion to authorize the Main Jail Complex Fencing and Gate Project in the amount of $3,415,520;
further, that the FY 2024 budget is amended as detailed in the attached Schedule A.
ITEM CATEGORY SPONSORED BY
Resolution Yolanda Smith Charles
INTRODUCTION AND BACKGROUND
In accordance with Purchasing Division policies and procedures, Facilities Planning and
Engineering (FP&E) and the Purchasing Division solicited a proposal for fencing and gates at the
Jail Complex (10 East), for annual competitively bid and selected contractors. George W. Auch Co.
of Pontiac, Michigan provided the best value bid.
The total project cost is $3,415,520, including $2,442,167 for fencing, gates, electrical, and
concrete, $147,100 for landscaping, $257,000 for access controls and intercoms, as well as
$569,253 for contingencies. Funding in the amount of $3,415,520 is available for transfer from the
FY2024 Capital Improvement Program/Building Improvement Fund (#40100) to the Project Work
Order Fund (#40400) for the Main Jail Complex Fencing and Gate Project (PRJ-7653).
POLICY ANALYSIS
This project includes labor, material and equipment to provide fencing to secure the Main Jail
Complex including vehicular and pedestrian secure entry gates and all earthwork, concrete work,
electrical and access control to accommodate new fencing and gates. Estimated start date is
September 2024. Estimated completion date is May 2025.
This was a request from the Sheriff’s Office when the previous security enhancement projects were
being implemented to address security concerns. There have been vehicle break-ins in the past at
both the Jail and East Annex as well as loitering around the employee areas and employee parking
lots. Sometimes these people confront the deputies on shift changes, and it creates unsafe
environments for the public and employees. The new layout also will alleviate traffic congestion at
shift change. The project will ensure that those who are not visiting the jail or east annex for a
business purpose are not able to access the facilities.
BUDGET AMENDMENT REQUIRED: Yes
Committee members can contact Michael Andrews, Policy and Fiscal Analysis Supervisor at
248.425.5572 or andrewsmb@oakgov.com or the department contact persons listed for additional
information.
CONTACT
Misty Raatz
ITEM REVIEW TRACKING
Aaron Snover, Board of Commissioners Created/Initiated - 7/19/2024
AGENDA DEADLINE: 07/18/2024 6:00 PM
ATTACHMENTS
1. Facilities_FY24_Jail Complex Exterior Fence Project_ScheduleA
2. Project Approval Information - Jail Fencing 6.14.24
COMMITTEE TRACKING
2024-07-10 Economic Development & Infrastructure - Forward to Finance
2024-07-10 Finance - Recommend to Board
2024-07-18 Full Board - Adopt
Motioned by: Commissioner Christine Long
Seconded by: Commissioner Ann Erickson Gault
Yes: David Woodward, Michael Spisz, Michael Gingell, Penny Luebs, Karen Joliat, Kristen
Nelson, Christine Long, Robert Hoffman, Philip Weipert, Gwen Markham, Angela Powell, Marcia
Gershenson, William Miller III, Yolanda Smith Charles, Charles Cavell, Brendan Johnson, Ajay
Raman, Ann Erickson Gault, Linnie Taylor (19)
No: None (0)
Abstain: None (0)
Absent: (0)
Passed
Oakland County, Michigan
FACILITIES MANAGEMENT/FACILITIES MAINTENANCE AND OPERATIONS - FY2024 JAIL COMPLEX EXTERIOR FENCE PROJECT
Schedule "A" DETAIL
R/E Fund Name Division Name
Fund #
(FND)Cost Center (CCN) #
Account #
(RC/SC)
Program #
(PRG)Grant ID (GRN) #
Project ID #
(PROJ)
Region
(REG)
Budget
Fund
Affiliate
(BFA)
Ledger
Account
Summary Account Title
FY 2024
Amendment
FY 2025
Amendment
FY 2026
Amendment
E Building Improvement Facilities Engineering Admin FND40100 CCN1040801 SC788001 PRG148020 BFA40400 788001 Transfer Out $(3,415,520.00)$-$-
Total Expenditures $(3,415,520.00)$-$-
R Project Work Order Facilities Engineering Admin FND40400 CCN1040801 RC695500 PRG148020 PROJ-17653 BFA40100 695500 Transfer In $3,415,520.00 $-$-
Total Revenues $3,415,520.00 $-$-
Project Manager: Stuart Rose
Project Name: 18-030 / Security Enhancements P3 Phase VII – Main Jail Complex Fencing
Project Scope (# of items, square footages, etc.): Labor, material and equipment to provide fencing to secure the Main
Jail Complex including vehicular and pedestrian secure entry gates and all earthwork, concrete work, electrical and
access control to accommodate new fencing and gates.
Budget: $3,415,520.00 Funding Source:
Extended Costs Approval Dates
Construction Cost: $2,442,167.00 BTF
Owner's Cost: $404,100.00 EG&I (Receive Bids)
Contingency: $569,253.00 EG&I (Award Contract)
: Finance
: Full Board
:
TOTAL: $3,415,520.00
Attached Cost Summary Attached Bid Summary
Estimated Start Date: September, 2024
Estimated Completion Date: May, 2025 Total Time: 9 months
Home City and State of each bidder:
Company City State
Auch Construction Pontiac MI
Doublejack Electric Troy MI
American Fence Warren MI
Hartwell Cement Oak Park MI
Notes:
Page 1 of 1
PROJECT APPROVAL INFORMATION
x x
Project Estimate
DESCRIPTION ESTIMATE
Estimate Date: 6/14/2024
FPE#: 18-030
WO#: 803829
FM Project Manager: ROSE, STUART
Project: Security Enhancements, Main Jail Complex Fencing
FM-730352 CONSTRUCTION
FM-730352-Sitework Auch - Fencing, Gates, Electrical, Concrete $2,442,167.00
FM-730352-Sitework FM&O - Retaining Wall $147,100.00
$2,589,267.00Total:CONSTRUCTION
FM-731689 SECURITY
FM-731689-SecurityCamerasCardReader EM&HS - Access Controls, Intercoms, RFID Readers $257,000.00
$257,000.00Total:SECURITY
FM-730359 CONTINGENCY
FM-730359-Contingency Owner's Contingency 15%$426,940.00
FM-730359-Contingency Inflationary Contingency 5%$142,313.00
$569,253.00Total:CONTINGENCY
GRAND TOTAL:
Subtotal Without Contingency:
Contingency:
$2,846,267.00
$569,253.00
$3,415,520.00