Loading...
HomeMy WebLinkAboutResolutions - 2024.07.18 - 41353 AGENDA ITEM: Jail Clinic HVAC System Replacement Project DEPARTMENT: Facilities Planning & Engineering MEETING: Board of Commissioners DATE: Thursday, July 18, 2024 6:00 PM - Click to View Agenda ITEM SUMMARY SHEET COMMITTEE REPORT TO BOARD Resolution #2024-4272 Motion to authorize the Jail Clinic HVAC System Replacement Project in the amount of $1,341,539; further, the FY 2024 budget is amended as detailed in the attached Schedule A. ITEM CATEGORY SPONSORED BY Resolution Yolanda Smith Charles INTRODUCTION AND BACKGROUND The Jail Clinic HVAC (heating, ventilation, air condition) System Replacement Project will include the replacement of the jail clinic air handling unit, distribution / mechanical ductwork revisions, new HVAC controls and components. In accordance with Purchasing Division policies and procedures, Facilities Maintenance and Operations (FM&O) and Purchasing solicited bids from annual competitively bid and selected contractors for the Jail Clinic HVAC System Replacement Project. Limbach Company LLC., provided the best value bid. The total project cost is $1,341,539, including $962,450 for materials and installation from Limbach Company, LLC., $13,500 for new roofing, patching and repair from Royal Roofing, $20,000 for interior demo, patching and repair from FM&O maintenance staff, $122,000 for mechanical and electrical engineering services from Hooker DeJong, INC., $223,589 for contingency. Funding in the amount of $1,341,539 is available for transfer from the FY 2024 Capital Improvement Program/Building Fund (#40100) to the Project Work Order Fund (#40400) for the Jail Clinic HVAC System Replacement Project (PRJ-17658). POLICY ANALYSIS The purpose of this project is to replace the Jail Clinic HVAC system with it's own unit to isolate airflow from other parts of the jail. This was a request made by the Sheriff's Office during the COVID-19 pandemic. BUDGET AMENDMENT REQUIRED: Yes Committee members can contact Michael Andrews, Policy and Fiscal Analysis Supervisor at 248.425.5572 or andrewsmb@oakgov.com or the department contact persons listed for additional information. CONTACT Misty Raatz ITEM REVIEW TRACKING Aaron Snover, Board of Commissioners Created/Initiated - 7/19/2024 AGENDA DEADLINE: 07/18/2024 6:00 PM ATTACHMENTS 1. Facilities_FY24_Jail Clinic HVAC System Replacement Project_ScheduleA 2. Jail Clinic AHU and HVAC Distribution Replacement Project ESTIMATE 06.17.24 COMMITTEE TRACKING 2024-07-10 Economic Development & Infrastructure - Forward to Finance 2024-07-10 Finance - Recommend to Board 2024-07-18 Full Board - Adopt Motioned by: Commissioner Christine Long Seconded by: Commissioner Ann Erickson Gault Yes: David Woodward, Michael Spisz, Michael Gingell, Penny Luebs, Karen Joliat, Kristen Nelson, Christine Long, Robert Hoffman, Philip Weipert, Gwen Markham, Angela Powell, Marcia Gershenson, William Miller III, Yolanda Smith Charles, Charles Cavell, Brendan Johnson, Ajay Raman, Ann Erickson Gault, Linnie Taylor (19) No: None (0) Abstain: None (0) Absent: (0) Passed Oakland County, Michigan FACILITIES MANAGEMENT/FACILITIES MAINTENANCE AND OPERATIONS - JAIL CLINIC HVAC SYSTEM REPLACEMENT PROJECT Schedule "A" DETAIL R/E Fund Name Division Name Fund # (FND)Cost Center (CCN) # Account # (RC/SC) Program # (PRG)Grant ID (GRN) # Project ID # (PROJ) Region (REG) Budget Fund Affiliate (BFA) Ledger Account Summary Account Title FY 2024 Amendment FY 2025 Amendment FY 2026 Amendment E Building Improvement Facilities Engineering Admin FND40100 CCN1040801 SC788001 PRG148020 BFA40400 788001 Transfer Out $(1,341,539)$-$- Total Expenditures $(1,341,539)$-$- R Project Work Order Facilities Engineering Admin FND40400 CCN1040801 RC695500 PRG148020 PROJ-17658 BFA40100 695500 Transfer In $1,341,539 $-$- Total Revenues $1,341,539 $-$- Project Estimate DESCRIPTION ESTIMATE Estimate Date: 6/17/2024 FPE#: WO#: 1175657 FM Project Manager: Stephen Foster Project: 033 Jail Clinic AHU & HVAC Distribution Replacement FM-730352 CONSTRUCTION FM-730352-HVAC Limbach Company, LLC.$962,450.00 FM-730352-Roofing Royal Roofing $13,500.00 FM-730352-PatchandPaint OC Maintenance Staff $20,000.00 $995,950.00Total:CONSTRUCTION FM-730359 CONTINGENCY FM-730359-Contingency Owner's Contingency 15%$167,692.00 FM-730359-Contingency Inflationary Contingency 5%$55,897.00 $223,589.00Total:CONTINGENCY Others CONSULTANTS FM-731444-MechanicalConsultant Hooker DeJong, INC.$122,000.00 $122,000.00Total:CONSULTANTS GRAND TOTAL: Subtotal Without Contingency: Contingency: $1,117,950.00 $223,589.00 $1,341,539.00 6/17/2024